| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $750/MONTH) | 30.00 | MTH |
9.00
| 8.00 | 1.00 | $750.00 | $750.00 |
| 7 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.39
| 0.37 | 0.02 | $170,000.00 | $3,400.00 |
| 9 | REMOVAL AND DISPOSAL OF LBP/LCP AND ACM DEBRIS | 1.00 | LS |
0.50
| 0.23 | 0.27 | $150,000.00 | $40,500.00 |
| 10 | IMPLEMENTATION OF THE ENVIRONMENTAL PLANS | 1.00 | LS |
0.50
| 0.23 | 0.27 | $50,000.00 | $13,500.00 |
| 11 | OFFICE FACILITIES | 30.00 | MTH |
9.00
| 8.00 | 1.00 | $4,000.00 | $4,000.00 |
| 25 | 2050-13 CUT AND REMOVE PORTIONS OF CONCRETE RISERS | 1.00 | LS |
1.00
| 0.90 | 0.10 | $100,000.00 | $10,000.00 |
| 26 | 2050-14 CUT AND REMOVE AUXILIARY SPILLWAY BOWL | 1.00 | LS |
0.95
| 0.37 | 0.58 | $200,000.00 | $116,000.00 |
| 27 | 2050-15 CUT AND REMOVE CREST SPILLWAY EXTENSION | 1.00 | LS |
0.25
| 0.00 | 0.25 | $550,000.00 | $137,500.00 |
| 32 | 2050-20 DEMOLISH TWO 5,000 GALLON WATER TANKS AND APPURTENANCES | 1.00 | LS |
0.75
| 0.50 | 0.25 | $25,000.00 | $6,250.00 |
| 33 | 2050-21 DEMOLISH GARAGE | 1.00 | LS |
0.95
| 0.00 | 0.95 | $15,000.00 | $14,250.00 |
| 34 | 2050-22 DEMOLISH DAM KEEPER'S HOUSE | 1.00 | LS |
0.20
| 0.00 | 0.20 | $50,000.00 | $10,000.00 |
| 39 | 2050-27 DEMOLISH STORAGE SHED (EAST) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $10,000.00 | $10,000.00 |
| 44 | 2140-2 IMPLEMENTATION OF CONTROL OF WATER PLAN | 1.00 | LS |
0.20
| 0.13 | 0.07 | $125,000.00 | $8,750.00 |
| 59 | 3300-3 OUTLET 2 PLATFORM | 1.00 | LS |
0.26
| 0.00 | 0.26 | $75,000.00 | $19,500.00 |
| 60 | 3300-4 HOIST LANDING PLATFORM AND CONCRETE RAMP | 1.00 | LS |
0.65
| 0.55 | 0.10 | $100,000.00 | $10,000.00 |
| 63 | 3300-9 PCC SLAB | 12.00 | CY |
12.00
| 2.00 | 10.00 | $2,750.00 | $27,500.00 |
| 64 | 3300-11 RETAINING WALL (ENTRANCE GATE) | 1.00 | LS |
0.80
| 0.26 | 0.54 | $75,000.00 | $40,500.00 |
| 65 | 3300-12 CONCRETE WALL (ADJACENT TO CONCRETE LINED CHANNEL) | 34.00 | CY |
9.00
| 4.00 | 5.00 | $1,300.00 | $6,500.00 |
| 67 | 3300-14 REPAIR ERODED CONCRETE | 1.00 | LS |
0.20
| 0.00 | 0.20 | $50,000.00 | $10,000.00 |
| 72 | 5400-1 SPILLWAY NOTCH BRIDGE | 1.00 | LS |
0.16
| 0.00 | 0.16 | $300,000.00 | $48,000.00 |
| 75 | 5500-5 RELOCATE TRASHRACKS | 1.00 | LS |
1.00
| 0.90 | 0.10 | $45,000.00 | $4,500.00 |
| 80 | 5500-11 SHIP'S LADDER PLATFORMS AND WALKWAYS (UPSTREAM) | 1.00 | LS |
0.08
| 0.00 | 0.08 | $380,000.00 | $30,400.00 |
| 89 | 13100-6 METAL POST GUARDRAIL (ROAD WIDENING) | 1.00 | LS |
1.00
| 0.92 | 0.08 | $30,000.00 | $2,400.00 |
| 93 | 15900-4 SLUICEWAY LINING | 1.00 | LS |
0.25
| 0.171 | 0.079 | $175,000.00 | $13,825.00 |
| 108 | ENTRANCE GATE (COMPLETE) | 1.00 | LS |
0.27
| 0.00 | 0.27 | $75,000.00 | $20,250.00 |
| 114 | CHANGEABLE MESSAGE SIGN (EACH) | 60.00 | MTH |
16.00
| 14.00 | 2.00 | $1,000.00 | $2,000.00 |
| S-2 | MODIFY RETAINING WALL ANCHORS | | T&M |
0.00
| 95,000.00 | -95,000.00 | $1.00 | ($95,000.00) |
| S-5 | INSTALL CLEANOUT FOR LEAKAGE LINE AT TOE OF DAM | | LS |
0.75
| 0.00 | 0.75 | $12,800.00 | $9,600.00 |
| S-7 | MODIFY RETAINING WALL ANCHORS | | LS |
0.69
| 0.00 | 0.69 | $143,250.00 | $98,842.50 |
| S-13 | REMOVE PROPANE TANK | | LS |
1.00
| 0.00 | 1.00 | $2,000.00 | $2,000.00 |
|