| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500.00/MTH) | 9.00 | MTH |
9.00
| 8.00 | 1.00 | $500.00 | $500.00 |
| 5 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.54
| 0.48 | 0.06 | $112,000.00 | $6,720.00 |
| 9 | SURFACE WATER DIVERSION STRUCTURE (STAGE ONE) | 1.00 | LS |
1.00
| 0.99 | 0.01 | $100,000.00 | $1,000.00 |
| 11 | REMOVE SURFACE WATER DIVERSION STRUCTURE (STAGE ONE) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $30,000.00 | $30,000.00 |
| 18 | IMPLEMENTATION OF THE SSHSP | 9.00 | MTH |
9.00
| 8.00 | 1.00 | $35.00 | $35.00 |
| 19 | OFFICE FACILITIES | 9.00 | MTH |
9.00
| 8.00 | 1.00 | $5,000.00 | $5,000.00 |
| 32 | TEMPORARY BALLAST (STAGE ONE) | 1.00 | LS |
1.00
| 0.79 | 0.21 | $30,000.00 | $6,300.00 |
| 35 | UNCLASSIFIED EXCAVATION | 1,299.00 | CY |
502.50
| 403.50 | 99.00 | $35.00 | $3,465.00 |
| 41 | CRUSHED MISCELLANEOUS BASE | 898.00 | CY |
361.50
| 196.00 | 165.50 | $40.00 | $6,620.00 |
| 42 | AC PAVEMENT | 1,343.00 | TON |
325.98
| 139.13 | 186.85 | $106.00 | $19,806.10 |
| 45 | ADJUST MANHOLE | 3.00 | EA |
2.00
| 1.00 | 1.00 | $960.00 | $960.00 |
| 46 | PCC PAVEMENT | 111.00 | CY |
102.00
| 73.00 | 29.00 | $230.00 | $6,670.00 |
| 50 | MINOR CONCRETE (BRIDGE CURB RAMP) | 2.00 | CY |
1.00
| 0.00 | 1.00 | $3,000.00 | $3,000.00 |
| 52 | CONCRETE BARRIER (TYPE 26 MODIFIED W/ SIDEWALK) | 150.00 | LF |
75.00
| 0.00 | 75.00 | $350.00 | $26,250.00 |
| 53 | CONCRETE BARRIER (TYPE 26 MODIFIED W/O SIDEWALK) | 30.00 | LF |
16.00
| 0.00 | 16.00 | $275.00 | $4,400.00 |
| 55 | CONCRETE BARRIER (TYPE 26 MODIFIED W/ SIDEWALK & STEEL COVER PLATE) | 31.00 | LF |
31.00
| 0.00 | 31.00 | $580.00 | $17,980.00 |
| 56 | AESTHETIC TREATMENT FOR CONCRETE BARRIER | 238.00 | LF |
111.00
| 0.00 | 111.00 | $200.00 | $22,200.00 |
| 59 | JOINT SEAL | 364.00 | LF |
145.60
| 0.00 | 145.60 | $28.00 | $4,076.80 |
| 64 | SHOTCRETE REINFORCED WITH WELDED WIRE FABRIC | 15.00 | SF |
15.00
| 0.00 | 15.00 | $665.00 | $9,975.00 |
| 67 | PCC CURB, TYPE A1-6 | 21.00 | LF |
21.00
| 7.00 | 14.00 | $80.00 | $1,120.00 |
| 68 | PCC CURB, TYPE A1-8 | 39.00 | LF |
10.00
| 0.00 | 10.00 | $80.00 | $800.00 |
| 70 | PCC CURB & GUTTER, TYPE A2-8 | 1,066.00 | LF |
269.50
| 193.00 | 76.50 | $36.00 | $2,754.00 |
| 71 | PCC WALK, 4" THICK | 6,253.00 | SF |
1,766.00
| 1,425.00 | 341.00 | $6.50 | $2,216.50 |
| 72 | PCC CURB RAMP, 4" THICK | 22.00 | SF |
328.00
| 306.00 | 22.00 | $18.00 | $396.00 |
| 75 | DETECTABLE WARNING SURFACE (BRIDGE CURB RAMP) | 33.00 | SF |
19.00
| 0.00 | 19.00 | $75.00 | $1,425.00 |
| 83 | 24" CONCRETE COLLAR | 1.00 | EA |
1.00
| 0.00 | 1.00 | $2,000.00 | $2,000.00 |
| 93 | TRAFFIC CONTROL (STAGE 2, PHASE 1) | 1.00 | LS |
1.00
| 0.90 | 0.10 | $2,100.00 | $210.00 |
| 99 | FLASHING ARROW SIGN | 2.00 | EA |
1.42
| 1.35 | 0.07 | $5,300.00 | $371.00 |
| 100 | CHANGEABLE MESSAGE SIGN | 3.00 | EA |
1.49
| 1.42 | 0.07 | $15,500.00 | $1,085.00 |
| 104 | 3" CONDUIT (GRC) | 85.00 | LF |
85.00
| 0.00 | 85.00 | $140.00 | $11,900.00 |
| 123 | TYPE 15 STANDARD | 2.00 | EA |
1.00
| 0.00 | 1.00 | $5,000.00 | $5,000.00 |
| 124 | TYPE 19 STANDARD | 1.00 | EA |
1.00
| 0.00 | 1.00 | $11,000.00 | $11,000.00 |
| 127 | TYPE 19 STANDARD FOUNDATION | 1.00 | EA |
1.00
| 0.00 | 1.00 | $6,000.00 | $6,000.00 |
| 131 | 15' LUMINAIRE MAST ARM | 4.00 | EA |
2.00
| 0.00 | 2.00 | $1,100.00 | $2,200.00 |
| 170 | 1-1/2" STREET LIGHT CONDUIT | 40.00 | LF |
40.00
| 30.00 | 10.00 | $58.00 | $580.00 |
| 171 | 3" STREET LIGHT CONDUIT | 748.00 | LF |
444.00
| 374.00 | 70.00 | $40.00 | $2,800.00 |
| 172 | WIRE #10 (STREET LIGHT) | 3,550.00 | LF |
990.00
| 0.00 | 990.00 | $1.10 | $1,089.00 |
| 173 | NO. 5 PULL BOX INCL PCC COVER (STREET LIGHT) | 10.00 | EA |
6.00
| 5.00 | 1.00 | $500.00 | $500.00 |
| 176 | TYPE 15 STANDARD WITH 15' MAST ARM AND 150 W HPS LUMINAIRE (COMPLETE) | 1.00 | EA |
1.00
| 0.00 | 1.00 | $7,000.00 | $7,000.00 |
| 177 | CONCRETE STREET LIGHT STANDARD WITH 100 W HPS LUMINAIRE (COMPLETE) | 1.00 | EA |
1.00
| 0.00 | 1.00 | $19,000.00 | $19,000.00 |
| 178 | CONCRETE STREET LIGHT STANDARD WITH 150 W HPS AND 50 W HPS LUMINAIRES (COMPLETE) | 4.00 | EA |
2.00
| 0.00 | 2.00 | $22,000.00 | $44,000.00 |
| 179 | CONCRETE PEDESTRIAN LIGHT STANDARD WITH 50 W HPS LUMINAIRE (COMPLETE) | 2.00 | EA |
1.00
| 0.00 | 1.00 | $10,000.00 | $10,000.00 |
| S-22 | ANCHOR BOLTS (TYPE 15TS BM) | | LS |
1.00
| 0.00 | 1.00 | $662.00 | $662.00 |
| S-25 | CONCRETE REMOVAL FOR SHORING STAGE 2 PHASE 1 | | T&M |
10,214.00
| 0.00 | 10,214.00 | $1.00 | $10,214.00 |
| S-31 | MODIFY AT&T UTILITY OPENING | | LS |
1.00
| 0.00 | 1.00 | $5,000.00 | $5,000.00 |
|