| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 3 | CONSTRUCTION SCHEDULE (AS-BUILT) (STIPULATED UNIT PRICE OF $1,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $1,000.00 | $1,000.00 |
| 11 | S-101 GATE GUARDS / FLAG PERSONS | 190.00 | DAYS |
96.00
| 90.00 | 6.00 | $475.00 | $2,850.00 |
| 21 | P-102 ADJUST WATER VALVE TO GRADE | 6.00 | EA |
9.00
| 6.00 | 3.00 | $600.00 | $1,800.00 |
| 23 | P-102 ADJUST MONITORING WELL TO GRADE | 2.00 | EA |
4.00
| 2.00 | 2.00 | $2,000.00 | $4,000.00 |
| 37 | P-403 BITUMINOUS SURFACE COURSE | 20,000.00 | TON |
18,913.45
| 18,893.45 | 20.00 | $66.76 | $1,335.20 |
| 44 | P-620 YELLOW MARKINGS (2 COATS) | 8,367.00 | SF |
8,452.00
| 2,902.00 | 5,550.00 | $1.46 | $8,103.00 |
| 45 | P-620 WHITE MARKINGS (2 COATS) | 2,902.00 | SF |
4,502.00
| 660.00 | 3,842.00 | $1.46 | $5,609.32 |
| 46 | P-620 BLACK MARKINGS (1 COAT) | 31,784.00 | SF |
32,715.00
| 33,100.00 | -385.00 | $1.10 | ($423.50) |