Los Angeles County Public Works
Project Management Division III
Progress Payment 8
Project Name: Altadena Monument Signs
Contractor: PK Construction
1227 Jacaranda place
Upland, CA 91784
Project ID: RDC0016115
Federal Number(s): None
Original Contract: $195,125.50
Awarded: 11/21/2017
Period Ending: 12/11/2019
Board Accepted: 3/29/2019
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
4CONCRETE REMOVAL (NON-REINFORCED)1.00CY 1.21 1.000.21$400.00$84.00
5UNCLASSIFIED EXCAVATION50.00CY 96.88 50.0046.88$20.00$937.60
10SOLAR ELECTRIC POWER ASSEMBLY2.00EA 2.00 0.251.75$16,500.00$28,875.00
11SOLAR LIGHTING8.00EA. 8.00 4.004.00$600.00$2,400.00
13TRENCHING AND SLEEVES FOR ELECTRICAL CONDUIT60.00LF 110.00 60.0050.00$18.00$900.00
143/4" ELECTROLIER LIGHTING CONDUIT130.00LF 163.00 130.0033.00$22.00$726.00
16CONCRETE PULL BOX4.00EA 5.00 4.001.00$400.00$400.00
17TRAFFIC CONTROL1.00LS 1.00 0.950.05$9,400.00$470.00
18FLASHING ARROW SIGN1.00EA 1.00 0.950.05$1,600.00$80.00
21FURNISH AND INSTALL SIGN8.00EA 11.00 8.003.00$1,500.00$4,500.00
26ROCK VENEER ON MORTAR BED299.00SF 409.00 400.998.01$18.00$144.18
27GALVANIZED POST W/ BASE PLATE, 3" O.D.1,710.00LB 1,716.00 1,710.006.00$7.50$45.00
28BOULDER6.00EA 9.00 6.003.00$400.00$1,200.00
S-2FURNISH ONE EXTRA SIGN EACH LS 1.00 0.001.00$475.00$475.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $212,450.60 $171,213.82 $41,236.78
Retained $10,622.53 $8,560.69 $2,061.84
Deducted $0.00 $0.00 $0.00
Due $201,828.07 $162,653.13 $39,174.94