| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $750/MONTH) | 30.00 | MTH |
12.00
| 11.00 | 1.00 | $750.00 | $750.00 |
| 7 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.45
| 0.43 | 0.02 | $170,000.00 | $3,400.00 |
| 11 | OFFICE FACILITIES | 30.00 | MTH |
12.00
| 10.00 | 2.00 | $4,000.00 | $8,000.00 |
| 21 | 2050-9 REMOVE CONRETE PLATFORM (OUTLET 2) | 1.00 | LS |
1.00
| 0.95 | 0.05 | $25,000.00 | $1,250.00 |
| 27 | 2050-15 CUT AND REMOVE CREST SPILLWAY EXTENSION | 1.00 | LS |
0.30
| 0.25 | 0.05 | $550,000.00 | $27,500.00 |
| 28 | 2050-16 CUT NEW SPILLWAY NOTCH | 1.00 | LS |
0.19
| 0.18 | 0.01 | $6,142,000.00 | $61,420.00 |
| 35 | 2050-23 DEMOLISH ROCK WALL (ADJACENT TO DAM KEEPER'S HOUSE) | 1.00 | LS |
1.00
| 0.90 | 0.10 | $20,000.00 | $2,000.00 |
| 44 | 2140-2 IMPLEMENTATION OF CONTROL OF WATER PLAN | 1.00 | LS |
0.35
| 0.31 | 0.04 | $125,000.00 | $5,000.00 |
| 47 | 2200-3 STRUCTURAL FILL FOR GABION RETAINING WALL, GENERATOR BUILDING (COMPLETE); HELIPORT AND APPURTENANCES | 332.00 | CY |
60.00
| 0.00 | 60.00 | $200.00 | $12,000.00 |
| 56 | 3230-1 POST-TENSIONED ANCHORS | 4.00 | EA |
0.50
| 0.00 | 0.50 | $25,000.00 | $12,500.00 |
| 61 | 3300-5 CONCRETE BRIDGE RAMP WITH ABUTMENTS | 1.00 | LS |
0.18
| 0.03 | 0.15 | $150,000.00 | $22,500.00 |
| 70 | 3361-2 SHOTCRETE REPAIRS (SPILLWAY IMPACT AREA) | 400.00 | SY |
50.00
| 0.00 | 50.00 | $750.00 | $37,500.00 |
| 80 | 5500-11 SHIP'S LADDER PLATFORMS AND WALKWAYS (UPSTREAM) | 1.00 | LS |
0.30
| 0.08 | 0.22 | $380,000.00 | $83,600.00 |
| 84 | 11290-1 RELOCATE HPU TO CONTROL HOUSE AND APPURTENANT WORK | 1.00 | LS |
0.20
| 0.07 | 0.13 | $150,000.00 | $19,500.00 |
| 105 | HELIPORT AND APPURTENANCES | 1.00 | LS |
0.75
| 0.00 | 0.75 | $150,000.00 | $112,500.00 |
| 107 | ELECTRICAL AND INSTRUMENTATION WORK | 1.00 | LS |
0.15
| 0.10 | 0.05 | $2,000,000.00 | $100,000.00 |
| 109 | SECTION R - UNCLASSIFIED EXCAVATION (ACCESS ROAD AND PARKING AREA PAVEMENT REPLACEMENT) | 662.00 | CY |
450.00
| 300.00 | 150.00 | $115.00 | $17,250.00 |
| 114 | CHANGEABLE MESSAGE SIGN (EACH) | 60.00 | MTH |
22.00
| 20.00 | 2.00 | $1,000.00 | $2,000.00 |
| S-1 | BELLY BOX FOR CABLE HOIST | | LS |
1.00
| 0.50 | 0.50 | $22,500.00 | $11,250.00 |
| S-4 | REMOVING REBARS AND CORE DRILLING AT TAIL HOIST PLATFORM | | T&M |
0.00
| 10,000.00 | -10,000.00 | $1.00 | ($10,000.00) |
| S-6 | 20K GAL WATER TANK & PILE WALL | | LS |
0.01
| 0.005 | 0.005 | $1,950,000.00 | $9,750.00 |
| S-7 | MODIFY RETAINING WALL ANCHORS | | LS |
0.70
| 0.69 | 0.01 | $143,250.00 | $1,432.50 |
| S-11 | REPAIR CRACKED AREA OF THE TAIL HOIST PLATFORM | | LS |
1.00
| 0.00 | 1.00 | $205,000.00 | $205,000.00 |
| S-16 | DIAMOND WIRE ROPE CUTTING | | LS |
0.25
| 0.00 | 0.25 | $135,000.00 | $33,750.00 |