Los Angeles County Public Works
Project Management Division III
Progress Payment 11
Project Name: Del Mar Avenue Bridge Replacement Over Alhambra Wash
Contractor: Shimmick Construction Company, Inc.
8201 Edgewater Drive, Suite 202
Oakland, CA 94621
Project ID: RDC0012721
Federal Number(s): BRLS-5217 (001)
Original Contract: $5,000,591.90
Awarded: 10/31/2017
Period Ending: 1/23/2019
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
794' PICKET RAILING (MODIFIED)238.00LF 119.00 0.00119.00$285.00$33,915.00
80AESTHETIC TREATMENT FOR PICKET RAILING238.00LF 119.00 0.00119.00$222.00$26,418.00
S-13INTERCEPT 2" ELECTRICAL PVC CONDUIT T&M 739.56 0.00739.56$1.00$739.56
S-26CONCRETE REMOVAL ON EXISTING ABUTMENT 2 WALL T&M 454.16 0.00454.16$1.00$454.16
S-27REPLACE DAMAGED CRASH CUSHION T&M 3,734.35 0.003,734.35$1.00$3,734.35
S-29MODIFY CATCH BASIN V=9.5 AT 7+65 T&M 28,838.76 0.0028,838.76$1.00$28,838.76
S-30SEAL GAP BETWEEN ABUTMENT STAGE 1 & 2 T&M 6,876.96 0.006,876.96$1.00$6,876.96
S-32ADDITIONAL CONSTRUCTION PHASE BETWEEN PHASE 1 & PAHSE 2 ON STAGE 2 T&M 10,000.00 0.0010,000.00$1.00$10,000.00
S-33MODIFY WINGWALL NO. 4 OVER 24" RCP T&M 1,867.47 0.001,867.47$1.00$1,867.47

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $2,928,860.96 $2,816,016.70 $112,844.26
Retained $145,068.04 $139,425.83 $5,642.21
Deducted $0.00 $0.00 $0.00
Due $2,783,792.92 $2,676,590.87 $107,202.05



Contact Office Engineer
Contractor Copy  
P Please consider the environment before printing this report.