Los Angeles County Public Works
Project Management Division III
Progress Payment 13
Project Name: San Gabriel Valley Airport Apron Pavement Rehabilitation - Phase 2
Contractor: Griffith Company
3050 East Birch Street
Brea, CA 92821
Project ID: APT5080452
Federal Number(s): None
Original Contract: $5,262,778.28
Awarded: 7/25/2017
Period Ending: 2/11/2019
Board Accepted: 2/20/2019
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MTH)10.00MTH 2.00 10.00-8.00$500.00($4,000.00)
24P-102 ADJUST ELECTRICAL/COMM HANDHOLE TO GRADE14.00EA 15.00 14.001.00$2,700.00$2,700.00
25P-102 ADJUST SEWER CLEANOUT TO GRADE2.00EA 4.00 2.002.00$800.00$1,600.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $4,927,316.87 $4,927,016.87 $300.00
Retained $243,900.88 $243,600.88 $300.00
Deducted $2,750.00 $2,750.00 $0.00
Due $4,680,665.99 $4,680,665.99 $0.00



Contact Office Engineer
Contractor Copy  
P Please consider the environment before printing this report.