Los Angeles County Public Works
Project Management Division III
Progress Payment 14
Project Name: San Gabriel Valley Airport Apron Pavement Rehabilitation - Phase 2
Contractor: Griffith Company
3050 East Birch Street
Brea, CA 92821
Project ID: APT5080452
Federal Number(s): None
Original Contract: $5,262,778.28
Awarded: 7/25/2017
Period Ending: 2/11/2019
Board Accepted: 2/20/2019
There is NO item progress this period

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $4,927,316.87 $4,927,316.87 $0.00
Retained $243,900.88 $243,900.88 $0.00
Deducted $2,750.00 $2,750.00 $0.00
Due $4,680,665.99 $4,680,665.99 $0.00