| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $750/MONTH) | 30.00 | MTH |
13.00
| 12.00 | 1.00 | $750.00 | $750.00 |
| 7 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.49
| 0.45 | 0.04 | $170,000.00 | $6,800.00 |
| 11 | OFFICE FACILITIES | 30.00 | MTH |
13.00
| 12.00 | 1.00 | $4,000.00 | $4,000.00 |
| 27 | 2050-15 CUT AND REMOVE CREST SPILLWAY EXTENSION | 1.00 | LS |
0.68
| 0.30 | 0.38 | $550,000.00 | $209,000.00 |
| 44 | 2140-2 IMPLEMENTATION OF CONTROL OF WATER PLAN | 1.00 | LS |
0.39
| 0.35 | 0.04 | $125,000.00 | $5,000.00 |
| 54 | 2900-1 WATER SYSTEM REPLACEMENT AND REHABILITATION | 1.00 | LS |
0.40
| 0.15 | 0.25 | $450,000.00 | $112,500.00 |
| 56 | 3230-1 POST-TENSIONED ANCHORS | 4.00 | EA |
2.00
| 0.50 | 1.50 | $25,000.00 | $37,500.00 |
| 73 | 5500-1 SHIP'S LADDER, PLATFORMS, AND WALKWAYS (DOWNSTREAM) | 1.00 | LS |
0.04
| 0.00 | 0.04 | $450,000.00 | $18,000.00 |
| 84 | 11290-1 RELOCATE HPU TO CONTROL HOUSE AND APPURTENANT WORK | 1.00 | LS |
0.35
| 0.20 | 0.15 | $150,000.00 | $22,500.00 |
| 91 | 14100-2 HOIST HEAD TOWER, TAIL TOWER, AND SYSTEM REHABILITATION | 1.00 | LS |
0.10
| 0.50 | -0.40 | $100,000.00 | ($40,000.00) |
| 107 | ELECTRICAL AND INSTRUMENTATION WORK | 1.00 | LS |
0.17
| 0.15 | 0.02 | $2,000,000.00 | $40,000.00 |
| 114 | CHANGEABLE MESSAGE SIGN (EACH) | 60.00 | MTH |
24.00
| 22.00 | 2.00 | $1,000.00 | $2,000.00 |
| S-6 | 20K GAL WATER TANK & PILE WALL | | LS |
0.12
| 0.01 | 0.11 | $1,950,000.00 | $214,500.00 |
| S-16 | DIAMOND WIRE ROPE CUTTING | | LS |
1.00
| 0.25 | 0.75 | $135,000.00 | $101,250.00 |
| S-18 | LEAD PAINT REMOVAL VALVE HOUSE #3 | | LS |
0.20
| 0.00 | 0.20 | $40,000.00 | $8,000.00 |
| S-19 | BACKFILL SEPTIC TANK & POTHOLE UTILITIES | | LS |
1.00
| 0.00 | 1.00 | $7,000.00 | $7,000.00 |
| S-21 | HELICOPTER TRANSPORT | | LS |
1.00
| 0.00 | 1.00 | $57,900.00 | $57,900.00 |
| S-22 | HAND CHIP SPILLWAY BUTTRESSES | | LS |
0.75
| 0.00 | 0.75 | $30,000.00 | $22,500.00 |
| S-25 | ADJUSTMENTS TO SLUICEWAY PIPE | | LS |
1.00
| 0.00 | 1.00 | $6,100.00 | $6,100.00 |