| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $750/MONTH) | 30.00 | MTH |
15.00
| 14.00 | 1.00 | $750.00 | $750.00 |
| 7 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.53
| 0.51 | 0.02 | $170,000.00 | $3,400.00 |
| 11 | OFFICE FACILITIES | 30.00 | MTH |
14.00
| 13.00 | 1.00 | $4,000.00 | $4,000.00 |
| 44 | 2140-2 IMPLEMENTATION OF CONTROL OF WATER PLAN | 1.00 | LS |
0.45
| 0.41 | 0.04 | $125,000.00 | $5,000.00 |
| 46 | 2140-4 IMPLEMENTATION OF EMERGENCY DEMOBILIZATION PLAN | 2.00 | EA |
1.00
| 0.00 | 1.00 | $5,000.00 | $5,000.00 |
| 105 | HELIPORT AND APPURTENANCES | 1.00 | LS |
0.85
| 0.75 | 0.10 | $150,000.00 | $15,000.00 |
| 107 | ELECTRICAL AND INSTRUMENTATION WORK | 1.00 | LS |
0.25
| 0.17 | 0.08 | $2,000,000.00 | $160,000.00 |
| 109 | SECTION R - UNCLASSIFIED EXCAVATION (ACCESS ROAD AND PARKING AREA PAVEMENT REPLACEMENT) | 662.00 | CY |
600.00
| 450.00 | 150.00 | $115.00 | $17,250.00 |
| 112 | SECTION R - PCC GUTTER (ROAD) | 878.00 | LF |
600.00
| 523.00 | 77.00 | $45.00 | $3,465.00 |
| 114 | CHANGEABLE MESSAGE SIGN (EACH) | 60.00 | MTH |
28.00
| 26.00 | 2.00 | $1,000.00 | $2,000.00 |
| S-6 | 20K GAL WATER TANK & PILE WALL | | LS |
0.28
| 0.15 | 0.13 | $1,950,000.00 | $253,500.00 |
| S-18 | LEAD PAINT REMOVAL VALVE HOUSE #3 | | LS |
0.40
| 0.25 | 0.15 | $40,000.00 | $6,000.00 |
| S-26 | HOIST TOWERS REVISED | | T&M |
210,000.00
| 195,000.00 | 15,000.00 | $1.00 | $15,000.00 |
| S-29 | RAIL SYSTEM AND LIFELINE FOR ACCESS ROAD | | LS |
0.50
| 0.00 | 0.50 | $210,000.00 | $105,000.00 |