| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500.00/MTH) | 9.00 | MTH |
10.00
| 9.00 | 1.00 | $500.00 | $500.00 |
| 5 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.60
| 0.54 | 0.06 | $112,000.00 | $6,720.00 |
| 8 | IMPLEMENTATION OF THE SURFACE WATER DIVERSION PLAN | 6.00 | MTH |
7.00
| 6.00 | 1.00 | $320.00 | $320.00 |
| 14 | EXCAVATION, TRANSPORTATION, AND DISPOSAL OF LEAD CONTAMINATED SOIL | 78.00 | TON |
78.00
| 24.00 | 54.00 | $130.00 | $7,020.00 |
| 18 | IMPLEMENTATION OF THE SSHSP | 9.00 | MTH |
10.00
| 9.00 | 1.00 | $35.00 | $35.00 |
| 19 | OFFICE FACILITIES | 9.00 | MTH |
11.00
| 10.00 | 1.00 | $5,000.00 | $5,000.00 |
| 23 | CONCRETE REMOVAL (NON-REINFORCED) | 760.00 | CY |
170.00
| 165.50 | 4.50 | $60.00 | $270.00 |
| 29 | BRIDGE REMOVAL (STAGE TWO) | 1.00 | LS |
0.35
| 0.10 | 0.25 | $100,000.00 | $25,000.00 |
| 30 | TEMPORARY VERTICAL SHORING (STAGE ONE) | 1.00 | LS |
1.00
| 0.97 | 0.03 | $225,000.00 | $6,750.00 |
| 31 | TEMPORARY VERTICAL SHORING (STAGE TWO) | 1.00 | LS |
0.46
| 0.05 | 0.41 | $200,000.00 | $82,000.00 |
| 42 | AC PAVEMENT | 1,343.00 | TON |
384.29
| 384.24 | 0.05 | $106.00 | $5.30 |
| 94 | TRAFFIC CONTROL (STAGE 2, PHASE 2) | 1.00 | LS |
0.60
| 0.50 | 0.10 | $2,400.00 | $240.00 |
| 99 | FLASHING ARROW SIGN | 2.00 | EA |
1.49
| 1.42 | 0.07 | $5,300.00 | $371.00 |
| 100 | CHANGEABLE MESSAGE SIGN | 3.00 | EA |
1.63
| 1.56 | 0.07 | $15,500.00 | $1,085.00 |
| 136 | REMOVE DETAIL 21 (PAINT) | 3,614.00 | LF |
1,903.00
| 750.00 | 1,153.00 | $1.00 | $1,153.00 |
| S-23 | REMOVAL OF EXISTING WINGWALL | | T&M |
11,898.17
| 7,915.63 | 3,982.54 | $1.00 | $3,982.54 |