| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $750/MONTH) | 30.00 | MTH |
17.00
| 16.00 | 1.00 | $750.00 | $750.00 |
| 7 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.57
| 0.55 | 0.02 | $170,000.00 | $3,400.00 |
| 27 | 2050-15 CUT AND REMOVE CREST SPILLWAY EXTENSION | 1.00 | LS |
0.98
| 0.90 | 0.08 | $550,000.00 | $44,000.00 |
| 44 | 2140-2 IMPLEMENTATION OF CONTROL OF WATER PLAN | 1.00 | LS |
0.50
| 0.48 | 0.02 | $125,000.00 | $2,500.00 |
| 54 | 2900-1 WATER SYSTEM REPLACEMENT AND REHABILITATION | 1.00 | LS |
0.54
| 0.45 | 0.09 | $450,000.00 | $40,500.00 |
| 69 | 3361-1 SHOTCRETE REPAIRS (MISCELLANEOUS) | 555.00 | SY |
116.00
| 0.00 | 116.00 | $850.00 | $98,600.00 |
| 72 | 5400-1 SPILLWAY NOTCH BRIDGE | 1.00 | LS |
0.75
| 0.50 | 0.25 | $300,000.00 | $75,000.00 |
| 81 | 11010-1 QUALITY REQUIREMENTS FOR EQUIPMENT | 1.00 | LS |
0.50
| 0.00 | 0.50 | $5,000.00 | $2,500.00 |
| 82 | 11020-1 INSPECTIONS AND TESTS FOR EQUIPMENT | 1.00 | LS |
0.50
| 0.00 | 0.50 | $5,000.00 | $2,500.00 |
| 83 | 11040-1 MANUFACTURER'S SERVICES | 1.00 | LS |
0.50
| 0.00 | 0.50 | $3,000.00 | $1,500.00 |
| 90 | 14100-1 CABLEWAY HOIST SYSTEM (COMPLETE) | 1.00 | LS |
1.00
| 0.80 | 0.20 | $1,200,000.00 | $240,000.00 |
| 104 | GENERATOR BUILDING (COMPLETE) | 1.00 | LS |
0.50
| 0.23 | 0.27 | $655,000.00 | $176,850.00 |
| 107 | ELECTRICAL AND INSTRUMENTATION WORK | 1.00 | LS |
0.40
| 0.35 | 0.05 | $2,000,000.00 | $100,000.00 |
| 114 | CHANGEABLE MESSAGE SIGN (EACH) | 60.00 | MTH |
32.00
| 30.00 | 2.00 | $1,000.00 | $2,000.00 |
| S-6 | 20K GAL WATER TANK & PILE WALL | | LS |
0.50
| 0.43 | 0.07 | $1,950,000.00 | $136,500.00 |
| S-22 | HAND CHIP SPILLWAY BUTTRESSES | | LS |
1.00
| 0.75 | 0.25 | $30,000.00 | $7,500.00 |
| S-24 | ACCESS WALKWAY TO DAM CREST | | LS |
0.70
| 0.00 | 0.70 | $17,200.00 | $12,040.00 |
| S-26A | REVISIONS TO HOIST TOWERS AND DELAY COSTS | | LS |
0.98
| 0.89 | 0.09 | $1,120,000.00 | $100,800.00 |
| S-29 | RAIL SYSTEM AND LIFELINE FOR ACCESS ROAD | | LS |
0.80
| 0.71 | 0.09 | $210,000.00 | $18,900.00 |
| S-29A | ACCESS ROAD REPAIRS | | T&M |
80,000.00
| 20,000.00 | 60,000.00 | $1.00 | $60,000.00 |
|