| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 5 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.72
| 0.66 | 0.06 | $112,000.00 | $6,720.00 |
| 10 | SURFACE WATER DIVERSION STRUCTURE (STAGE TWO) | 1.00 | LS |
0.96
| 0.95 | 0.01 | $65,000.00 | $650.00 |
| 18 | IMPLEMENTATION OF THE SSHSP | 9.00 | MTH |
12.00
| 11.00 | 1.00 | $35.00 | $35.00 |
| 21 | CLEARING AND GRUBBING | 1.00 | LS |
1.00
| 0.75 | 0.25 | $8,000.00 | $2,000.00 |
| 29 | BRIDGE REMOVAL (STAGE TWO) | 1.00 | LS |
1.00
| 0.60 | 0.40 | $100,000.00 | $40,000.00 |
| 31 | TEMPORARY VERTICAL SHORING (STAGE TWO) | 1.00 | LS |
0.80
| 0.70 | 0.10 | $200,000.00 | $20,000.00 |
| 33 | TEMPORARY BALLAST (STAGE TWO) | 1.00 | LS |
0.76
| 0.75 | 0.01 | $10,000.00 | $100.00 |
| 36 | STRUCTURE EXCAVATION (BRIDGE) | 2,170.00 | CY |
2,069.00
| 1,538.50 | 530.50 | $37.00 | $19,628.50 |
| 37 | STRUCTURE BACKFILL (BRIDGE) | 2,000.00 | CY |
1,195.00
| 820.00 | 375.00 | $50.00 | $18,750.00 |
| 48 | STRUCTURE CONCRETE (FOOTING) | 437.00 | CY |
312.00
| 182.00 | 130.00 | $300.00 | $39,000.00 |
| 57 | BAR REINFORCING STEEL (BRIDGE) | 196,000.00 | LB |
112,701.00
| 79,701.00 | 33,000.00 | $1.18 | $38,940.00 |
| 58 | JOINT SEAL, TYPE A | 285.00 | LF |
72.38
| 0.00 | 72.38 | $83.00 | $6,007.54 |
| 94 | TRAFFIC CONTROL (STAGE 2, PHASE 2) | 1.00 | LS |
0.80
| 0.70 | 0.10 | $2,400.00 | $240.00 |
| 97 | TEMPORARY RAILING (TYPE K) | 500.00 | LF |
528.00
| 525.00 | 3.00 | $31.00 | $93.00 |
| 99 | FLASHING ARROW SIGN | 2.00 | EA |
1.63
| 1.56 | 0.07 | $5,300.00 | $371.00 |
| 100 | CHANGEABLE MESSAGE SIGN | 3.00 | EA |
1.77
| 1.70 | 0.07 | $15,500.00 | $1,085.00 |
| S-39 | OFFICE FACILITY | | MTH |
1.50
| 0.50 | 1.00 | $2,500.00 | $2,500.00 |
| S-40 | IMPLEMENTATION OF SURFACE WATER DIVERSION PLAN PHASE 2 | | MTH |
2.00
| 1.00 | 1.00 | $1,342.42 | $1,342.42 |