| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $750/MONTH) | 30.00 | MTH |
19.00
| 18.00 | 1.00 | $750.00 | $750.00 |
| 7 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.61
| 0.59 | 0.02 | $170,000.00 | $3,400.00 |
| 11 | OFFICE FACILITIES | 30.00 | MTH |
18.00
| 17.00 | 1.00 | $4,000.00 | $4,000.00 |
| 26 | 2050-14 CUT AND REMOVE AUXILIARY SPILLWAY BOWL | 1.00 | LS |
1.00
| 0.95 | 0.05 | $200,000.00 | $10,000.00 |
| 28 | 2050-16 CUT NEW SPILLWAY NOTCH | 1.00 | LS |
0.24
| 0.20 | 0.04 | $6,142,000.00 | $245,680.00 |
| 29 | 2050-17 CUT AND REMOVE 30" PARAPET WALL | 1.00 | LS |
1.00
| 0.00 | 1.00 | $25,000.00 | $25,000.00 |
| 31 | 2050-19 DEMOLISH HPU HOUSE AND PLATFORM | 1.00 | LS |
0.20
| 0.00 | 0.20 | $155,000.00 | $31,000.00 |
| 44 | 2140-2 IMPLEMENTATION OF CONTROL OF WATER PLAN | 1.00 | LS |
0.56
| 0.53 | 0.03 | $125,000.00 | $3,750.00 |
| 54 | 2900-1 WATER SYSTEM REPLACEMENT AND REHABILITATION | 1.00 | LS |
0.60
| 0.54 | 0.06 | $450,000.00 | $27,000.00 |
| 73 | 5500-1 SHIP'S LADDER, PLATFORMS, AND WALKWAYS (DOWNSTREAM) | 1.00 | LS |
0.25
| 0.04 | 0.21 | $450,000.00 | $94,500.00 |
| 74 | 5500-2 SLUICEWAY DRAWBRIDGE | 1.00 | LS |
0.75
| 0.60 | 0.15 | $33,000.00 | $4,950.00 |
| 92 | 14200-1 REMOVE, REHABILITATE, AND REINSTALL 5-TON JIB CRANE | 1.00 | LS |
0.10
| 0.00 | 0.10 | $250,000.00 | $25,000.00 |
| 101 | OUTLET 2 VALVES AND ALL APPURTENANT WORK | 1.00 | LS |
0.46
| 0.36 | 0.10 | $250,000.00 | $25,000.00 |
| 102 | OUTLET 3 VALVES AND ALL APPURTENANT WORK | 1.00 | LS |
0.46
| 0.36 | 0.10 | $250,000.00 | $25,000.00 |
| 103 | OUTLET 4 VALVES AND ALL APPURTENANT WORK | 1.00 | LS |
0.46
| 0.36 | 0.10 | $250,000.00 | $25,000.00 |
| 104 | GENERATOR BUILDING (COMPLETE) | 1.00 | LS |
0.70
| 0.60 | 0.10 | $655,000.00 | $65,500.00 |
| 107 | ELECTRICAL AND INSTRUMENTATION WORK | 1.00 | LS |
0.50
| 0.40 | 0.10 | $2,000,000.00 | $200,000.00 |
| 114 | CHANGEABLE MESSAGE SIGN (EACH) | 60.00 | MTH |
36.00
| 34.00 | 2.00 | $1,000.00 | $2,000.00 |
| S-6 | 20K GAL WATER TANK & PILE WALL | | LS |
0.65
| 0.60 | 0.05 | $1,950,000.00 | $97,500.00 |
| S-28 | GENERATOR BUILDING REVISED | | LS |
0.80
| 0.60 | 0.20 | $96,000.00 | $19,200.00 |
| S-29A | ACCESS ROAD REPAIRS | | T&M |
211,690.00
| 99,971.00 | 111,719.00 | $1.00 | $111,719.00 |
| S-29B | CONCRETE DEMOLITION IMPACT | | LS |
0.06
| 0.00 | 0.06 | $173,992.00 | $10,439.52 |
| S-29C | CMB, PLACED ON SAD POOL ROAD | | CY |
80.00
| 0.00 | 80.00 | $273.09 | $21,847.20 |
|