| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $750/MONTH) | 30.00 | MTH |
20.00
| 19.00 | 1.00 | $750.00 | $750.00 |
| 7 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.63
| 0.61 | 0.02 | $170,000.00 | $3,400.00 |
| 11 | OFFICE FACILITIES | 30.00 | MTH |
19.00
| 18.00 | 1.00 | $4,000.00 | $4,000.00 |
| 15 | 2050-3 REMOVE WALKWAYS | 1,076.00 | LF |
375.00
| 560.00 | -185.00 | $65.00 | ($12,025.00) |
| 28 | 2050-16 CUT NEW SPILLWAY NOTCH | 1.00 | LS |
0.36
| 0.24 | 0.12 | $6,142,000.00 | $737,040.00 |
| 44 | 2140-2 IMPLEMENTATION OF CONTROL OF WATER PLAN | 1.00 | LS |
0.59
| 0.56 | 0.03 | $125,000.00 | $3,750.00 |
| 48 | 2200-7 EXCAVATION FOR SHOTCRETE REPAIRS (MISCELLANEOUS) | 555.00 | SY |
555.00
| 400.00 | 155.00 | $55.00 | $8,525.00 |
| 49 | 2200-8 EXCAVATION FOR SHOTCRETE REPAIRS (SPILLWAY IMPACT AREA) | 400.00 | SY |
180.00
| 0.00 | 180.00 | $95.00 | $17,100.00 |
| 56 | 3230-1 POST-TENSIONED ANCHORS | 4.00 | EA |
4.00
| 2.00 | 2.00 | $25,000.00 | $50,000.00 |
| 69 | 3361-1 SHOTCRETE REPAIRS (MISCELLANEOUS) | 555.00 | SY |
490.00
| 400.00 | 90.00 | $850.00 | $76,500.00 |
| 70 | 3361-2 SHOTCRETE REPAIRS (SPILLWAY IMPACT AREA) | 400.00 | SY |
100.00
| 50.00 | 50.00 | $750.00 | $37,500.00 |
| 73 | 5500-1 SHIP'S LADDER, PLATFORMS, AND WALKWAYS (DOWNSTREAM) | 1.00 | LS |
0.50
| 0.25 | 0.25 | $450,000.00 | $112,500.00 |
| 104 | GENERATOR BUILDING (COMPLETE) | 1.00 | LS |
0.80
| 0.70 | 0.10 | $655,000.00 | $65,500.00 |
| 106 | CONTROL BUILDING IMPROVEMENTS | 1.00 | LS |
0.20
| 0.00 | 0.20 | $100,000.00 | $20,000.00 |
| 107 | ELECTRICAL AND INSTRUMENTATION WORK | 1.00 | LS |
0.55
| 0.50 | 0.05 | $2,000,000.00 | $100,000.00 |
| 114 | CHANGEABLE MESSAGE SIGN (EACH) | 60.00 | MTH |
38.00
| 36.00 | 2.00 | $1,000.00 | $2,000.00 |
| S-6 | 20K GAL WATER TANK & PILE WALL | | LS |
0.68
| 0.65 | 0.03 | $1,950,000.00 | $58,500.00 |
| S-28 | GENERATOR BUILDING REVISED | | LS |
0.85
| 0.80 | 0.05 | $96,000.00 | $4,800.00 |
| S-29A | ACCESS ROAD REPAIRS | | T&M |
238,550.00
| 211,690.00 | 26,860.00 | $1.00 | $26,860.00 |
| S-29B | CONCRETE DEMOLITION IMPACT | | LS |
0.22
| 0.06 | 0.16 | $173,992.00 | $27,838.72 |
| S-29C | CMB, PLACED ON SAD POOL ROAD | | CY |
200.00
| 80.00 | 120.00 | $273.09 | $32,770.80 |
| S-29F | HAULING BRIDGE STEEL SECTIONS | | LS |
1.00
| 0.00 | 1.00 | $6,840.00 | $6,840.00 |
|