| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500.00/MTH) | 9.00 | MTH |
14.00
| 13.00 | 1.00 | $500.00 | $500.00 |
| 5 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.90
| 0.84 | 0.06 | $112,000.00 | $6,720.00 |
| 10 | SURFACE WATER DIVERSION STRUCTURE (STAGE TWO) | 1.00 | LS |
0.99
| 0.98 | 0.01 | $65,000.00 | $650.00 |
| 18 | IMPLEMENTATION OF THE SSHSP | 9.00 | MTH |
15.00
| 14.00 | 1.00 | $35.00 | $35.00 |
| 23 | CONCRETE REMOVAL (NON-REINFORCED) | 760.00 | CY |
293.00
| 219.00 | 74.00 | $60.00 | $4,440.00 |
| 24 | CONCRETE REMOVAL (REINFORCED) | 12.00 | CY |
8.00
| 5.00 | 3.00 | $214.00 | $642.00 |
| 31 | TEMPORARY VERTICAL SHORING (STAGE TWO) | 1.00 | LS |
1.00
| 0.80 | 0.20 | $200,000.00 | $40,000.00 |
| 33 | TEMPORARY BALLAST (STAGE TWO) | 1.00 | LS |
0.79
| 0.78 | 0.01 | $10,000.00 | $100.00 |
| 35 | UNCLASSIFIED EXCAVATION | 1,299.00 | CY |
1,022.50
| 502.50 | 520.00 | $35.00 | $18,200.00 |
| 37 | STRUCTURE BACKFILL (BRIDGE) | 2,000.00 | CY |
2,000.00
| 1,900.00 | 100.00 | $50.00 | $5,000.00 |
| 40 | GEOCOMPOSITE WALL DRAIN | 4,860.00 | SF |
4,860.00
| 4,385.00 | 475.00 | $6.00 | $2,850.00 |
| 41 | CRUSHED MISCELLANEOUS BASE | 898.00 | CY |
600.50
| 361.50 | 239.00 | $40.00 | $9,560.00 |
| 47 | STRUCTURE CONCRETE (BRIDGE) | 734.00 | CY |
734.00
| 625.00 | 109.00 | $895.00 | $97,555.00 |
| 49 | MINOR CONCRETE (DRAINAGE PAD) | 2.00 | CY |
2.00
| 0.25 | 1.75 | $1,900.00 | $3,325.00 |
| 51 | MINOR CONCRETE (BRIDGE SIDEWALK) | 2.00 | CY |
2.00
| 0.00 | 2.00 | $3,000.00 | $6,000.00 |
| 52 | CONCRETE BARRIER (TYPE 26 MODIFIED W/ SIDEWALK) | 150.00 | LF |
123.00
| 75.00 | 48.00 | $350.00 | $16,800.00 |
| 54 | CONCRETE BARRIER (TYPE 26 MODIFIED W/ CURB RAMP) | 27.00 | LF |
27.00
| 0.00 | 27.00 | $285.00 | $7,695.00 |
| 56 | AESTHETIC TREATMENT FOR CONCRETE BARRIER | 238.00 | LF |
186.00
| 111.00 | 75.00 | $200.00 | $15,000.00 |
| 57 | BAR REINFORCING STEEL (BRIDGE) | 196,000.00 | LB |
196,000.00
| 171,301.00 | 24,699.00 | $1.18 | $29,144.82 |
| 62 | CATCH BASIN PER STD PLAN 300, W=7 | 2.00 | EA |
1.00
| 0.00 | 1.00 | $6,600.00 | $6,600.00 |
| 75 | DETECTABLE WARNING SURFACE (BRIDGE CURB RAMP) | 33.00 | SF |
33.00
| 19.00 | 14.00 | $75.00 | $1,050.00 |
| 94 | TRAFFIC CONTROL (STAGE 2, PHASE 2) | 1.00 | LS |
1.00
| 0.95 | 0.05 | $2,400.00 | $120.00 |
| 97 | TEMPORARY RAILING (TYPE K) | 500.00 | LF |
537.00
| 534.00 | 3.00 | $31.00 | $93.00 |
| 99 | FLASHING ARROW SIGN | 2.00 | EA |
1.84
| 1.77 | 0.07 | $5,300.00 | $371.00 |
| 100 | CHANGEABLE MESSAGE SIGN | 3.00 | EA |
1.98
| 1.91 | 0.07 | $15,500.00 | $1,085.00 |
| S-32 | ADDITIONAL CONSTRUCTION PHASE BETWEEN PHASE 1 & PAHSE 2 ON STAGE 2 | | T&M |
20,126.43
| 10,000.00 | 10,126.43 | $1.00 | $10,126.43 |
| S-38 | REPLACEMENT OF UNEVEN PAVEMENT S/B DEL MAR AVE | | T&M |
24,493.82
| 0.00 | 24,493.82 | $1.00 | $24,493.82 |
| S-39 | OFFICE FACILITY | | MTH |
4.50
| 3.50 | 1.00 | $2,500.00 | $2,500.00 |
| S-40 | IMPLEMENTATION OF SURFACE WATER DIVERSION PLAN PHASE 2 | | MTH |
5.00
| 4.00 | 1.00 | $1,342.42 | $1,342.42 |
| S-43 | CONCRETE REMOVAL STAGE 2 PHASE 2 | | T&M |
66,875.08
| 0.00 | 66,875.08 | $1.00 | $66,875.08 |
|