Los Angeles County Public Works
Project Management Division III
Progress Payment 7
Project Name: Mulholland Highway Over Triunfo Creek Bridge 1180 On-System, et al. (2018WOOLSEYFIRE)
Contractor: John S. Meek Company, Inc.
14732 South Maple Avenue
Gardena, CA 90248
Project ID: RDC0016358
Federal Number(s): ER - TBD
Original Contract: $2,124,824.00
Awarded: 1/31/2019
Period Ending: 10/6/2019
Board Accepted: 12/23/2019
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
S-1RENTAL, INSTALLATION, AND MAINTENANCE OF THE TEMPORARY BRIDGE AND PICKET RAILING FOR 12 MONTHS LS 0.87 0.800.07$583,900.00$40,873.00
S-11EXTENDED OFFICE FACILITY MTH 2.00 0.002.00$1,625.00$3,250.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $1,983,691.69 $1,939,568.69 $44,123.00
Retained $99,184.61 $96,978.46 $2,206.15
Deducted $0.00 $0.00 $0.00
Due $1,884,507.08 $1,842,590.23 $41,916.85



Contact Office Engineer
Chandra McLoud (626) 458-3165
Contractor Copy  