| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $750/MONTH) | 30.00 | MTH |
22.00
| 21.00 | 1.00 | $750.00 | $750.00 |
| 7 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.67
| 0.65 | 0.02 | $170,000.00 | $3,400.00 |
| 11 | OFFICE FACILITIES | 30.00 | MTH |
21.00
| 20.00 | 1.00 | $4,000.00 | $4,000.00 |
| 14 | 2050-2 REMOVE EXISTING HANDRAILS | 426.00 | LF |
235.00
| 200.00 | 35.00 | $35.00 | $1,225.00 |
| 19 | 2050-7 REMOVE STILLING WELL AND RECORDER HOUSE | 1.00 | LS |
0.90
| 0.00 | 0.90 | $10,000.00 | $9,000.00 |
| 28 | 2050-16 CUT NEW SPILLWAY NOTCH | 1.00 | LS |
0.64
| 0.51 | 0.13 | $6,142,000.00 | $798,460.00 |
| 44 | 2140-2 IMPLEMENTATION OF CONTROL OF WATER PLAN | 1.00 | LS |
0.65
| 0.62 | 0.03 | $125,000.00 | $3,750.00 |
| 57 | 3300-1 OGEE SPILLWAY | 1.00 | LS |
0.04
| 0.02 | 0.02 | $5,250,000.00 | $105,000.00 |
| 61 | 3300-5 CONCRETE BRIDGE RAMP WITH ABUTMENTS | 1.00 | LS |
0.55
| 0.50 | 0.05 | $150,000.00 | $7,500.00 |
| 68 | 3300-15 PARAPET WALL | 4.00 | CY |
4.00
| 0.00 | 4.00 | $4,000.00 | $16,000.00 |
| 70 | 3361-2 SHOTCRETE REPAIRS (SPILLWAY IMPACT AREA) | 400.00 | SY |
300.00
| 150.00 | 150.00 | $750.00 | $112,500.00 |
| 72 | 5400-1 SPILLWAY NOTCH BRIDGE | 1.00 | LS |
1.00
| 0.75 | 0.25 | $300,000.00 | $75,000.00 |
| 104 | GENERATOR BUILDING (COMPLETE) | 1.00 | LS |
0.87
| 0.85 | 0.02 | $655,000.00 | $13,100.00 |
| 107 | ELECTRICAL AND INSTRUMENTATION WORK | 1.00 | LS |
0.60
| 0.58 | 0.02 | $2,000,000.00 | $40,000.00 |
| 114 | CHANGEABLE MESSAGE SIGN (EACH) | 60.00 | MTH |
42.00
| 40.00 | 2.00 | $1,000.00 | $2,000.00 |
| S-6 | 20K GAL WATER TANK & PILE WALL | | LS |
0.85
| 0.68 | 0.17 | $1,950,000.00 | $331,500.00 |
| S-28 | GENERATOR BUILDING REVISED | | LS |
0.95
| 0.85 | 0.10 | $96,000.00 | $9,600.00 |
| S-29A | ACCESS ROAD REPAIRS | | T&M |
373,473.00
| 316,067.00 | 57,406.00 | $1.00 | $57,406.00 |
| S-29B | CONCRETE DEMOLITION IMPACT | | LS |
0.58
| 0.40 | 0.18 | $173,992.00 | $31,318.56 |
| S-29C | CMB, PLACED ON SAD POOL ROAD | | CY |
700.00
| 550.00 | 150.00 | $273.09 | $40,963.50 |
| S-36 | SHOTCRETE SETTLEMENT | | LS |
1.00
| 0.00 | 1.00 | $40,000.00 | $40,000.00 |
| S-38 | EXTEND LEAKAGE LINE AT EAST ARMORING | | LS |
0.50
| 0.00 | 0.50 | $6,360.00 | $3,180.00 |
| S-40 | STILLING WELL CLEANUP | | LS |
1.00
| 0.50 | 0.50 | $9,000.00 | $4,500.00 |
|