| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 5 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
1.00
| 0.96 | 0.04 | $112,000.00 | $4,480.00 |
| 18 | IMPLEMENTATION OF THE SSHSP | 9.00 | MTH |
17.00
| 16.00 | 1.00 | $35.00 | $35.00 |
| 23 | CONCRETE REMOVAL (NON-REINFORCED) | 760.00 | CY |
444.00
| 293.00 | 151.00 | $60.00 | $9,060.00 |
| 24 | CONCRETE REMOVAL (REINFORCED) | 12.00 | CY |
10.15
| 8.00 | 2.15 | $214.00 | $460.10 |
| 35 | UNCLASSIFIED EXCAVATION | 1,299.00 | CY |
1,345.00
| 1,022.50 | 322.50 | $35.00 | $11,287.50 |
| 41 | CRUSHED MISCELLANEOUS BASE | 898.00 | CY |
934.00
| 600.50 | 333.50 | $40.00 | $13,340.00 |
| 42 | AC PAVEMENT | 1,343.00 | TON |
979.74
| 384.29 | 595.45 | $106.00 | $63,117.70 |
| 79 | 4' PICKET RAILING (MODIFIED) | 238.00 | LF |
238.00
| 119.00 | 119.00 | $285.00 | $33,915.00 |
| 80 | AESTHETIC TREATMENT FOR PICKET RAILING | 238.00 | LF |
238.00
| 119.00 | 119.00 | $222.00 | $26,418.00 |
| 95 | TRAFFIC CONTROL (STAGE 3, PHASE 2) | 1.00 | LS |
0.50
| 0.00 | 0.50 | $3,300.00 | $1,650.00 |
| 96 | TRAFFIC CONTROL (STAGE 3, PHASE 1) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $3,300.00 | $3,300.00 |
| 99 | FLASHING ARROW SIGN | 2.00 | EA |
1.98
| 1.91 | 0.07 | $5,300.00 | $371.00 |
| 100 | CHANGEABLE MESSAGE SIGN | 3.00 | EA |
2.07
| 2.00 | 0.07 | $15,500.00 | $1,085.00 |
| 125 | TYPE 26 STANDARD | 1.00 | EA |
1.00
| 0.00 | 1.00 | $12,800.00 | $12,800.00 |
| 129 | 25' SIGNAL MAST ARM | 1.00 | EA |
1.00
| 0.00 | 1.00 | $3,000.00 | $3,000.00 |
| 130 | 40' SIGNAL MAST ARM | 1.00 | EA |
1.00
| 0.00 | 1.00 | $3,500.00 | $3,500.00 |
| 131 | 15' LUMINAIRE MAST ARM | 4.00 | EA |
3.50
| 3.00 | 0.50 | $1,100.00 | $550.00 |
| 136 | REMOVE DETAIL 21 (PAINT) | 3,614.00 | LF |
2,733.00
| 1,903.00 | 830.00 | $1.00 | $830.00 |
| 139 | REMOVE DETAIL 27B (PAINT) | 5,939.00 | LF |
1,667.00
| 552.00 | 1,115.00 | $1.00 | $1,115.00 |
| 140 | REMOVE DETAIL 28 (PAINT) | 748.00 | LF |
160.00
| 0.00 | 160.00 | $1.25 | $200.00 |
| 143 | REMOVE DETAIL 38A (PAINT) | 1,053.00 | LF |
480.00
| 100.00 | 380.00 | $1.10 | $418.00 |
| 145 | REMOVE PAVEMENT MARKINGS (PAINT) | 303.00 | SF |
303.00
| 288.00 | 15.00 | $2.00 | $30.00 |
| 146 | REMOVE 12" STRIPING (PAINT) | 160.00 | LF |
107.00
| 77.00 | 30.00 | $2.50 | $75.00 |
| 148 | DETAIL 21 (ONE-COAT PAINT) | 2,470.00 | LF |
2,419.00
| 2,069.00 | 350.00 | $0.55 | $192.50 |
| 149 | DETAIL 24 (ONE-COAT PAINT) | 1,859.00 | LF |
1,859.00
| 92.00 | 1,767.00 | $0.35 | $618.45 |
| 150 | DETAIL 27B (ONE-COAT PAINT) | 5,418.00 | LF |
3,335.00
| 2,655.00 | 680.00 | $0.25 | $170.00 |
| S-39 | OFFICE FACILITY | | MTH |
6.50
| 5.50 | 1.00 | $2,500.00 | $2,500.00 |
|