Los Angeles County Public Works
Project Management Division III
Progress Payment 22
Project Name: Del Mar Avenue Bridge Replacement Over Alhambra Wash
Contractor: Shimmick Construction Company, Inc.
8201 Edgewater Drive, Suite 202
Oakland, CA 94621
Project ID: RDC0012721
Federal Number(s): BRLS-5217 (001)
Original Contract: $5,000,591.90
Awarded: 10/31/2017
Period Ending: 1/20/2020
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500.00/MTH)9.00MTH 19.00 18.001.00$500.00$500.00
18IMPLEMENTATION OF THE SSHSP9.00MTH 19.00 18.001.00$35.00$35.00
45ADJUST MANHOLE3.00EA 3.00 2.001.00$960.00$960.00
63REINFORCED CONCRETE BLOCK WALL PER STD PLAN 601, TYPE 1 (H=6')52.00LF 41.00 0.0041.00$500.00$20,500.00
70PCC CURB & GUTTER, TYPE A2-81,066.00LF 926.50 921.505.00$36.00$180.00
1043" CONDUIT (GRC)85.00LF 195.00 85.00110.00$140.00$15,400.00
1054" CONDUIT (SCH 80 PVC)220.00LF 382.00 330.0052.00$70.00$3,640.00
1701-1/2" STREET LIGHT CONDUIT40.00LF 85.00 45.0040.00$58.00$2,320.00
1713" STREET LIGHT CONDUIT748.00LF 748.00 744.004.00$40.00$160.00
S-4RECONSTRUCT SEWER MANHOLE SOUTHWEST CORNER COMMERCAIL CENTER & DEL MAR AVE T&M 6,998.31 7,000.00-1.69$1.00($1.69)
S-20HANDICAP RAMPS AT PARK & RIDE T&M 12,073.69 12,060.3513.34$1.00$13.34

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $5,321,848.00 $5,278,141.35 $43,706.65
Retained $264,717.39 $262,532.06 $2,185.33
Deducted $0.00 $0.00 $0.00
Due $5,057,130.61 $5,015,609.29 $41,521.32



Contact Office Engineer
Contractor Copy  
P Please consider the environment before printing this report.