| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $750/MONTH) | 30.00 | MTH |
25.00
| 24.00 | 1.00 | $750.00 | $750.00 |
| 7 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.73
| 0.71 | 0.02 | $170,000.00 | $3,400.00 |
| 11 | OFFICE FACILITIES | 30.00 | MTH |
24.00
| 23.00 | 1.00 | $4,000.00 | $4,000.00 |
| 28 | 2050-16 CUT NEW SPILLWAY NOTCH | 1.00 | LS |
1.00
| 0.92 | 0.08 | $6,142,000.00 | $491,360.00 |
| 44 | 2140-2 IMPLEMENTATION OF CONTROL OF WATER PLAN | 1.00 | LS |
0.74
| 0.71 | 0.03 | $125,000.00 | $3,750.00 |
| 48 | 2200-7 EXCAVATION FOR SHOTCRETE REPAIRS (MISCELLANEOUS) | 555.00 | SY |
640.00
| 555.00 | 85.00 | $55.00 | $4,675.00 |
| 54 | 2900-1 WATER SYSTEM REPLACEMENT AND REHABILITATION | 1.00 | LS |
0.62
| 0.60 | 0.02 | $450,000.00 | $9,000.00 |
| 57 | 3300-1 OGEE SPILLWAY | 1.00 | LS |
0.08
| 0.06 | 0.02 | $5,250,000.00 | $105,000.00 |
| 61 | 3300-5 CONCRETE BRIDGE RAMP WITH ABUTMENTS | 1.00 | LS |
1.00
| 0.95 | 0.05 | $150,000.00 | $7,500.00 |
| 69 | 3361-1 SHOTCRETE REPAIRS (MISCELLANEOUS) | 555.00 | SY |
640.00
| 530.00 | 110.00 | $850.00 | $93,500.00 |
| 70 | 3361-2 SHOTCRETE REPAIRS (SPILLWAY IMPACT AREA) | 400.00 | SY |
380.00
| 300.00 | 80.00 | $750.00 | $60,000.00 |
| 73 | 5500-1 SHIP'S LADDER, PLATFORMS, AND WALKWAYS (DOWNSTREAM) | 1.00 | LS |
0.95
| 0.90 | 0.05 | $450,000.00 | $22,500.00 |
| 92 | 14200-1 REMOVE, REHABILITATE, AND REINSTALL 5-TON JIB CRANE | 1.00 | LS |
0.15
| 0.10 | 0.05 | $250,000.00 | $12,500.00 |
| 104 | GENERATOR BUILDING (COMPLETE) | 1.00 | LS |
0.90
| 0.87 | 0.03 | $655,000.00 | $19,650.00 |
| 107 | ELECTRICAL AND INSTRUMENTATION WORK | 1.00 | LS |
0.67
| 0.65 | 0.02 | $2,000,000.00 | $40,000.00 |
| 114 | CHANGEABLE MESSAGE SIGN (EACH) | 60.00 | MTH |
46.00
| 44.00 | 2.00 | $1,000.00 | $2,000.00 |
| S-6 | 20K GAL WATER TANK & PILE WALL | | LS |
0.86
| 0.85 | 0.01 | $1,950,000.00 | $19,500.00 |
| S-26B | HEAD TOWER SHEAVE MODIFICATIONS | | LS |
1.00
| 0.00 | 1.00 | $10,380.00 | $10,380.00 |
| S-29A | ACCESS ROAD REPAIRS | | T&M |
510,498.00
| 470,000.00 | 40,498.00 | $1.00 | $40,498.00 |
| S-29B | CONCRETE DEMOLITION IMPACT | | LS |
1.00
| 0.95 | 0.05 | $173,992.00 | $8,699.60 |
| S-29C | CMB, PLACED ON SAD POOL ROAD | | CY |
1,267.00
| 1,077.00 | 190.00 | $273.09 | $51,887.10 |
| S-29G | PUMPABLE CONCRETE MIX DESIGN | | T&M |
0.00
| 63,000.00 | -63,000.00 | $1.00 | ($63,000.00) |
| S-29H | PUMPABLE MIX DESIGNS, TESTS, & MOCK-UPS | | LS |
0.90
| 0.00 | 0.90 | $99,000.00 | $89,100.00 |
| S-43 | INSTALL TWO JOINT METER BOXES AT BRIDGE RAMP | | LS |
0.75
| 0.05 | 0.70 | $5,300.00 | $3,710.00 |
|