Los Angeles County Public Works
Project Management Division III
Progress Payment 24
Project Name: Santa Anita Dam Spillway Modification Project
Contractor: Kiewit Infrastructure West Company
10704 Shoemaker Avenue
Santa Fe Springs, CA 90670-4024
Project ID: FCC0001251
Federal Number(s): None
Original Contract: $25,773,160.00
Awarded: 10/18/2017
Period Ending: 2/29/2020
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $750/MONTH)30.00MTH 26.00 25.001.00$750.00$750.00
5UST CLOSURE REPORT (STIPULATED UNIT PRICE OF $2,500)1.00LS 0.50 0.000.50$2,500.00$1,250.00
7IMPLEMENTATION OF THE SWPPP1.00LS 0.75 0.730.02$170,000.00$3,400.00
11OFFICE FACILITIES30.00MTH 25.00 24.001.00$4,000.00$4,000.00
422050-30 REMOVE EXISTING EMERGENCY GENERATOR AND 100 GALLON FUEL TANK1.00LS 0.50 0.000.50$15,000.00$7,500.00
442140-2 IMPLEMENTATION OF CONTROL OF WATER PLAN1.00LS 0.76 0.740.02$125,000.00$2,500.00
542900-1 WATER SYSTEM REPLACEMENT AND REHABILITATION1.00LS 0.65 0.620.03$450,000.00$13,500.00
573300-1 OGEE SPILLWAY1.00LS 0.20 0.080.12$5,250,000.00$630,000.00
735500-1 SHIP'S LADDER, PLATFORMS, AND WALKWAYS (DOWNSTREAM)1.00LS 1.00 0.950.05$450,000.00$22,500.00
775500-8 HORIZONTAL LIFELINE (COMPLETE)1.00LS 1.00 0.001.00$35,000.00$35,000.00
785500-9 DAM CREST HANDRAIL300.00LF 100.00 0.00100.00$200.00$20,000.00
9616050-9 RELOCATE DADAS AND OTHER CONDUITS ONTO BRIDGE1.00LS 1.00 0.001.00$12,000.00$12,000.00
104GENERATOR BUILDING (COMPLETE)1.00LS 0.95 0.900.05$655,000.00$32,750.00
107ELECTRICAL AND INSTRUMENTATION WORK1.00LS 0.75 0.670.08$2,000,000.00$160,000.00
114CHANGEABLE MESSAGE SIGN (EACH)60.00MTH 48.00 46.002.00$1,000.00$2,000.00
S-620K GAL WATER TANK & PILE WALL LS 0.88 0.860.02$1,950,000.00$39,000.00
S-28GENERATOR BUILDING REVISED LS 1.00 0.950.05$96,000.00$4,800.00
S-29AACCESS ROAD REPAIRS T&M 559,759.00 510,498.0049,261.00$1.00$49,261.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $23,288,022.53 $22,247,811.53 $1,040,211.00
Retained $1,163,526.15 $1,111,515.60 $52,010.55
Deducted $0.00 $0.00 $0.00
Due $22,124,496.38 $21,136,295.93 $988,200.45



Contact Office Engineer
Contractor Copy  
P Please consider the environment before printing this report.