Los Angeles County Public Works
Project Management Division III
Progress Payment 12
Project Name: Mulholland Highway Over Triunfo Creek Bridge 1180 On-System, et al. (2018WOOLSEYFIRE)
Contractor: John S. Meek Company, Inc.
14732 South Maple Avenue
Gardena, CA 90248
Project ID: RDC0016358
Federal Number(s): ER - TBD
Original Contract: $2,124,824.00
Awarded: 1/31/2019
Period Ending: 3/6/2020
Board Accepted: 12/23/2019
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
S-2MONTHLY RENTAL AND MAINTENANCE OF TEMPORARY BRIDGE AND PICKET RAILING (AFTER INITIAL 12 MONTHS) MTH 1.00 0.001.00$20,600.00$20,600.00
S-11EXTENDED OFFICE FACILITY MTH 7.00 6.001.00$1,625.00$1,625.00
S-15REVISED TRAFFIC SIGNAL PLAN LS 1.00 0.900.10$324,000.00$32,400.00

DEDUCTION DETAIL

DescriptionUnitTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
AMBER STEEL TRUST FUND REPORTEA 0.00 1.00-1.00$1,000.00 ($1,000.00)

FINANCIAL SUMMARY

  Total Previous Current
Earned $2,430,037.16 $2,375,412.16 $54,625.00
Retained $121,501.88 $118,770.63 $2,731.25
Deducted $0.00 $1,000.00 ($1,000.00)
Due $2,308,535.28 $2,255,641.53 $52,893.75



Contact Office Engineer
Chandra McLoud (626) 458-3165
Contractor Copy  
P Please consider the environment before printing this report.