Progress Payment 24
Project Name: Del Mar Avenue Bridge Replacement Over Alhambra Wash
Contractor: Shimmick Construction Company, Inc.
8201 Edgewater Drive, Suite 202
Oakland, CA 94621
Project ID: RDC0012721
Federal Number(s): BRLS-5217 (001)
Original Contract: $5,000,591.90
Awarded: 10/31/2017
Period Ending: 3/20/2020
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
23CONCRETE REMOVAL (NON-REINFORCED)760.00CY 445.00 444.001.00$60.00$60.00
72PCC CURB RAMP, 4" THICK22.00SF 538.00 518.0020.00$18.00$360.00
S-41TRAFFIC CONTROL STAGE 2, 3, 4 T&M 6,087.68 0.006,087.68$1.00$6,087.68
S-44REMOVAL OF RIVER ROCK, BOULDERS & BURIED CONCRETE T&M 27,922.42 0.0027,922.42$1.00$27,922.42
S-46INSTALLATION OF #8 CONDUCTOR WIRE T&M 2,570.40 0.002,570.40$1.00$2,570.40
S-48INSTALLATION OF REGULATORY SIGNS T&M 3,132.24 0.003,132.24$1.00$3,132.24
S-49TS ANCHOR BOLTS AT BARRIER ELECTROLIER T&M 1,570.32 0.001,570.32$1.00$1,570.32
S-54CURB RAMP MODIFICATIONS T&M 29,911.20 0.0029,911.20$1.00$29,911.20

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $5,510,291.22 $5,438,676.96 $71,614.26
Retained $138,694.77 $136,904.41 $1,790.36
Deducted $0.00 $0.00 $0.00
Due $5,371,596.45 $5,301,772.55 $69,823.90