| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $750/MONTH) | 30.00 | MTH |
27.00
| 26.00 | 1.00 | $750.00 | $750.00 |
| 7 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.77
| 0.75 | 0.02 | $170,000.00 | $3,400.00 |
| 11 | OFFICE FACILITIES | 30.00 | MTH |
26.00
| 25.00 | 1.00 | $4,000.00 | $4,000.00 |
| 31 | 2050-19 DEMOLISH HPU HOUSE AND PLATFORM | 1.00 | LS |
0.40
| 0.20 | 0.20 | $155,000.00 | $31,000.00 |
| 44 | 2140-2 IMPLEMENTATION OF CONTROL OF WATER PLAN | 1.00 | LS |
0.78
| 0.76 | 0.02 | $125,000.00 | $2,500.00 |
| 48 | 2200-7 EXCAVATION FOR SHOTCRETE REPAIRS (MISCELLANEOUS) | 555.00 | SY |
759.00
| 640.00 | 119.00 | $55.00 | $6,545.00 |
| 54 | 2900-1 WATER SYSTEM REPLACEMENT AND REHABILITATION | 1.00 | LS |
0.75
| 0.65 | 0.10 | $450,000.00 | $45,000.00 |
| 57 | 3300-1 OGEE SPILLWAY | 1.00 | LS |
0.31
| 0.20 | 0.11 | $5,250,000.00 | $577,500.00 |
| 69 | 3361-1 SHOTCRETE REPAIRS (MISCELLANEOUS) | 555.00 | SY |
750.00
| 640.00 | 110.00 | $850.00 | $93,500.00 |
| 73 | 5500-1 SHIP'S LADDER, PLATFORMS, AND WALKWAYS (DOWNSTREAM) | 1.00 | LS |
0.95
| 1.00 | -0.05 | $450,000.00 | ($22,500.00) |
| 80 | 5500-11 SHIP'S LADDER PLATFORMS AND WALKWAYS (UPSTREAM) | 1.00 | LS |
0.40
| 0.30 | 0.10 | $380,000.00 | $38,000.00 |
| 84 | 11290-1 RELOCATE HPU TO CONTROL HOUSE AND APPURTENANT WORK | 1.00 | LS |
0.60
| 0.35 | 0.25 | $150,000.00 | $37,500.00 |
| 114 | CHANGEABLE MESSAGE SIGN (EACH) | 60.00 | MTH |
50.00
| 48.00 | 2.00 | $1,000.00 | $2,000.00 |
| S-6 | 20K GAL WATER TANK & PILE WALL | | LS |
0.90
| 0.88 | 0.02 | $1,950,000.00 | $39,000.00 |
| S-29A | ACCESS ROAD REPAIRS | | T&M |
611,338.00
| 559,759.00 | 51,579.00 | $1.00 | $51,579.00 |
| S-51A | OGEE SURFACE PREPARATION | | LS |
0.20
| 0.00 | 0.20 | $6,700.00 | $1,340.00 |