Los Angeles County Public Works
Project Management Division III
Progress Payment 13
Project Name: Mulholland Highway Over Triunfo Creek Bridge 1180 On-System, et al. (2018WOOLSEYFIRE)
Contractor: John S. Meek Company, Inc.
14732 South Maple Avenue
Gardena, CA 90248
Project ID: RDC0016358
Federal Number(s): ER - TBD
Original Contract: $2,124,824.00
Awarded: 1/31/2019
Period Ending: 4/6/2020
Board Accepted: 12/23/2019
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
S-2MONTHLY RENTAL AND MAINTENANCE OF TEMPORARY BRIDGE AND PICKET RAILING (AFTER INITIAL 12 MONTHS) MTH 2.00 1.001.00$20,600.00$20,600.00
S-11EXTENDED OFFICE FACILITY MTH 8.00 7.001.00$1,625.00$1,625.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $2,452,262.16 $2,430,037.16 $22,225.00
Retained $122,613.13 $121,501.88 $1,111.25
Deducted $0.00 $0.00 $0.00
Due $2,329,649.03 $2,308,535.28 $21,113.75