| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $750/MONTH) | 30.00 | MTH |
28.00
| 27.00 | 1.00 | $750.00 | $750.00 |
| 7 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.79
| 0.77 | 0.02 | $170,000.00 | $3,400.00 |
| 11 | OFFICE FACILITIES | 30.00 | MTH |
27.00
| 26.00 | 1.00 | $4,000.00 | $4,000.00 |
| 14 | 2050-2 REMOVE EXISTING HANDRAILS | 426.00 | LF |
400.00
| 235.00 | 165.00 | $35.00 | $5,775.00 |
| 31 | 2050-19 DEMOLISH HPU HOUSE AND PLATFORM | 1.00 | LS |
0.60
| 0.40 | 0.20 | $155,000.00 | $31,000.00 |
| 44 | 2140-2 IMPLEMENTATION OF CONTROL OF WATER PLAN | 1.00 | LS |
0.80
| 0.78 | 0.02 | $125,000.00 | $2,500.00 |
| 57 | 3300-1 OGEE SPILLWAY | 1.00 | LS |
0.50
| 0.31 | 0.19 | $5,250,000.00 | $997,500.00 |
| 78 | 5500-9 DAM CREST HANDRAIL | 300.00 | LF |
200.00
| 100.00 | 100.00 | $200.00 | $20,000.00 |
| 110 | SECTION R - AC PAVEMENT | 826.00 | TON |
704.00
| 546.78 | 157.22 | $120.00 | $18,866.40 |
| S-6 | 20K GAL WATER TANK & PILE WALL | | LS |
0.92
| 0.90 | 0.02 | $1,950,000.00 | $39,000.00 |
| S-29A | ACCESS ROAD REPAIRS | | T&M |
670,869.00
| 611,338.00 | 59,531.00 | $1.00 | $59,531.00 |
| S-43 | INSTALL TWO JOINT METER BOXES AT BRIDGE RAMP | | LS |
0.90
| 0.75 | 0.15 | $5,300.00 | $795.00 |
| S-50 | IMPLEMENTATION OF PUMPABLE OGEE MIX DESIGN | | LS |
0.50
| 0.00 | 0.50 | $75,000.00 | $37,500.00 |
| S-51A | OGEE SURFACE PREPARATION | | LS |
0.25
| 0.20 | 0.05 | $6,700.00 | $335.00 |
| S-52 | WATER CURING THE OGEE CONCRETE SURFACE | | LS |
0.25
| 0.00 | 0.25 | $16,150.00 | $4,037.50 |
| S-54 | MOBILIZATION, GRADING, AC BERM | | LS |
1.00
| 0.00 | 1.00 | $8,800.00 | $8,800.00 |