Los Angeles County Public Works
Project Management Division III
Progress Payment 26
Project Name: Del Mar Avenue Bridge Replacement Over Alhambra Wash
Contractor: Shimmick Construction Company, Inc.
8201 Edgewater Drive, Suite 202
Oakland, CA 94621
Project ID: RDC0012721
Federal Number(s): BRLS-5217 (001)
Original Contract: $5,000,591.90
Awarded: 10/31/2017
Period Ending: 5/20/2020
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
S-52REPLACE 11" ANCHOR BOLTS T&M 1,883.28 0.001,883.28$1.00$1,883.28
S-60CONSTRUCT MOD CB AND RECONSTRUCT, ROADWAY 10+00 - 11+50 LS 1.00 0.300.70$206,000.00$144,200.00
S-62SCE DELAY  LS 1.00 0.001.00$37,642.00$37,642.00
S-64RECONSTRUCT DRIVEWAY LS 17,349.64 8,674.828,674.82$1.00$8,674.82
S-65RELOCATE 4" SL CONDUIT LS 0.375 0.000.375$5,000.00$1,875.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $5,832,339.96 $5,638,064.86 $194,275.10
Retained $146,745.99 $141,889.11 $4,856.88
Deducted $0.00 $0.00 $0.00
Due $5,685,593.97 $5,496,175.75 $189,418.22



Contact Office Engineer
Contractor Copy  
P Please consider the environment before printing this report.