| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $750/MONTH) | 30.00 | MTH |
29.00
| 28.00 | 1.00 | $750.00 | $750.00 |
| 7 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.81
| 0.79 | 0.02 | $170,000.00 | $3,400.00 |
| 11 | OFFICE FACILITIES | 30.00 | MTH |
28.00
| 27.00 | 1.00 | $4,000.00 | $4,000.00 |
| 16 | 2050-4 REMOVE 30" HOLLOW JET VALVES, GATE VALVES, AND APPURTENANCES | 1.00 | LS |
1.00
| 0.00 | 1.00 | $25,000.00 | $25,000.00 |
| 17 | 2050-5 REMOVE 18" HOLLOW JET VALVE, 20" GATE VALVE, AND APPURTENANCES | 1.00 | LS |
0.50
| 0.00 | 0.50 | $25,000.00 | $12,500.00 |
| 31 | 2050-19 DEMOLISH HPU HOUSE AND PLATFORM | 1.00 | LS |
0.80
| 0.60 | 0.20 | $155,000.00 | $31,000.00 |
| 42 | 2050-30 REMOVE EXISTING EMERGENCY GENERATOR AND 100 GALLON FUEL TANK | 1.00 | LS |
0.75
| 0.50 | 0.25 | $15,000.00 | $3,750.00 |
| 44 | 2140-2 IMPLEMENTATION OF CONTROL OF WATER PLAN | 1.00 | LS |
0.82
| 0.80 | 0.02 | $125,000.00 | $2,500.00 |
| 54 | 2900-1 WATER SYSTEM REPLACEMENT AND REHABILITATION | 1.00 | LS |
0.78
| 0.75 | 0.03 | $450,000.00 | $13,500.00 |
| 57 | 3300-1 OGEE SPILLWAY | 1.00 | LS |
0.74
| 0.50 | 0.24 | $5,250,000.00 | $1,260,000.00 |
| 80 | 5500-11 SHIP'S LADDER PLATFORMS AND WALKWAYS (UPSTREAM) | 1.00 | LS |
0.50
| 0.40 | 0.10 | $380,000.00 | $38,000.00 |
| 94 | 15900-5 PENSTOCK CRACK REPAIRS (OUTLETS 3 AND 4) | 1.00 | LS |
0.50
| 0.00 | 0.50 | $35,000.00 | $17,500.00 |
| 103 | OUTLET 4 VALVES AND ALL APPURTENANT WORK | 1.00 | LS |
0.90
| 0.46 | 0.44 | $250,000.00 | $110,000.00 |
| 108 | ENTRANCE GATE (COMPLETE) | 1.00 | LS |
0.95
| 0.80 | 0.15 | $75,000.00 | $11,250.00 |
| 114 | CHANGEABLE MESSAGE SIGN (EACH) | 60.00 | MTH |
54.00
| 50.00 | 4.00 | $1,000.00 | $4,000.00 |
| S-6 | 20K GAL WATER TANK & PILE WALL | | LS |
0.97
| 0.92 | 0.05 | $1,950,000.00 | $97,500.00 |
| S-10 | 2- 3" AIR RELEASE VALVES FOR VALVE #3 AND #4 | | LS |
0.50
| 0.00 | 0.50 | $4,823.00 | $2,411.50 |
| S-26A | REVISIONS TO HOIST TOWERS AND DELAY COSTS | | LS |
1.00
| 0.99 | 0.01 | $1,120,000.00 | $11,200.00 |
| S-29A | ACCESS ROAD REPAIRS | | T&M |
730,074.00
| 670,869.00 | 59,205.00 | $1.00 | $59,205.00 |
| S-29C | CMB, PLACED ON SAD POOL ROAD | | CY |
1,300.00
| 1,267.00 | 33.00 | $273.09 | $9,011.97 |
| S-33 | FIRE SPRINKLER SYSTEM | | LS |
0.75
| 0.15 | 0.60 | $34,360.00 | $20,616.00 |
| S-48 | CHILLER FOR OGEE PUMPABLE CONCRETE MIX | | T&M |
58,000.00
| 0.00 | 58,000.00 | $1.00 | $58,000.00 |
| S-50 | IMPLEMENTATION OF PUMPABLE OGEE MIX DESIGN | | LS |
0.75
| 0.50 | 0.25 | $75,000.00 | $18,750.00 |
| S-51A | OGEE SURFACE PREPARATION | | LS |
0.50
| 0.25 | 0.25 | $6,700.00 | $1,675.00 |
| S-52 | WATER CURING THE OGEE CONCRETE SURFACE | | LS |
0.75
| 0.25 | 0.50 | $16,150.00 | $8,075.00 |
| S-56 | INSTALL ADDITIONAL FENCING AT WATER TANK SITE | | LS |
1.00
| 0.00 | 1.00 | $10,000.00 | $10,000.00 |
|