| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $750/MONTH) | 30.00 | MTH |
30.00
| 29.00 | 1.00 | $750.00 | $750.00 |
| 7 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.83
| 0.81 | 0.02 | $170,000.00 | $3,400.00 |
| 11 | OFFICE FACILITIES | 30.00 | MTH |
29.00
| 28.00 | 1.00 | $4,000.00 | $4,000.00 |
| 31 | 2050-19 DEMOLISH HPU HOUSE AND PLATFORM | 1.00 | LS |
0.95
| 0.80 | 0.15 | $155,000.00 | $23,250.00 |
| 42 | 2050-30 REMOVE EXISTING EMERGENCY GENERATOR AND 100 GALLON FUEL TANK | 1.00 | LS |
0.90
| 0.75 | 0.15 | $15,000.00 | $2,250.00 |
| 44 | 2140-2 IMPLEMENTATION OF CONTROL OF WATER PLAN | 1.00 | LS |
0.84
| 0.82 | 0.02 | $125,000.00 | $2,500.00 |
| 57 | 3300-1 OGEE SPILLWAY | 1.00 | LS |
0.90
| 0.74 | 0.16 | $5,250,000.00 | $840,000.00 |
| 80 | 5500-11 SHIP'S LADDER PLATFORMS AND WALKWAYS (UPSTREAM) | 1.00 | LS |
0.65
| 0.50 | 0.15 | $380,000.00 | $57,000.00 |
| 86 | 13100-3 STAINLESS STEEL CABLE HANDRAIL ADJACENT TO GAGE BOARDS | 120.00 | LF |
100.00
| 30.00 | 70.00 | $155.00 | $10,850.00 |
| 94 | 15900-5 PENSTOCK CRACK REPAIRS (OUTLETS 3 AND 4) | 1.00 | LS |
1.00
| 0.50 | 0.50 | $35,000.00 | $17,500.00 |
| 100 | VALVE HOUSE IMPROVEMENTS | 1.00 | LS |
0.10
| 0.06 | 0.04 | $125,000.00 | $5,000.00 |
| 102 | OUTLET 3 VALVES AND ALL APPURTENANT WORK | 1.00 | LS |
0.90
| 0.46 | 0.44 | $250,000.00 | $110,000.00 |
| 106 | CONTROL BUILDING IMPROVEMENTS | 1.00 | LS |
0.40
| 0.20 | 0.20 | $100,000.00 | $20,000.00 |
| 107 | ELECTRICAL AND INSTRUMENTATION WORK | 1.00 | LS |
0.80
| 0.75 | 0.05 | $2,000,000.00 | $100,000.00 |
| 114 | CHANGEABLE MESSAGE SIGN (EACH) | 60.00 | MTH |
56.00
| 54.00 | 2.00 | $1,000.00 | $2,000.00 |
| S-10 | 2- 3" AIR RELEASE VALVES FOR VALVE #3 AND #4 | | LS |
1.00
| 0.50 | 0.50 | $4,823.00 | $2,411.50 |
| S-29A | ACCESS ROAD REPAIRS | | T&M |
789,645.00
| 730,074.00 | 59,571.00 | $1.00 | $59,571.00 |
| S-50 | IMPLEMENTATION OF PUMPABLE OGEE MIX DESIGN | | LS |
1.00
| 0.75 | 0.25 | $75,000.00 | $18,750.00 |
| S-51A | OGEE SURFACE PREPARATION | | LS |
1.00
| 0.50 | 0.50 | $6,700.00 | $3,350.00 |
| S-52 | WATER CURING THE OGEE CONCRETE SURFACE | | LS |
1.00
| 0.75 | 0.25 | $16,150.00 | $4,037.50 |
| S-53 | ISOLATION VALVE FOR RELIEF QUARTERS BUILDING | | LS |
0.90
| 0.00 | 0.90 | $4,500.00 | $4,050.00 |
| S-58 | TAIL HOIST WALKWAY SUPORT | | LS |
1.00
| 0.00 | 1.00 | $7,500.00 | $7,500.00 |
|