| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $750/MONTH) | 30.00 | MTH |
31.00
| 30.00 | 1.00 | $750.00 | $750.00 |
| 7 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.85
| 0.83 | 0.02 | $170,000.00 | $3,400.00 |
| 10 | IMPLEMENTATION OF THE ENVIRONMENTAL PLANS | 1.00 | LS |
0.77
| 0.75 | 0.02 | $50,000.00 | $1,000.00 |
| 11 | OFFICE FACILITIES | 30.00 | MTH |
30.00
| 29.00 | 1.00 | $4,000.00 | $4,000.00 |
| 17 | 2050-5 REMOVE 18" HOLLOW JET VALVE, 20" GATE VALVE, AND APPURTENANCES | 1.00 | LS |
1.00
| 0.50 | 0.50 | $25,000.00 | $12,500.00 |
| 24 | 2050-12 REMOVE PARTIALLY EXPOSED WATERLINE | 1.00 | LS |
0.50
| 0.40 | 0.10 | $20,000.00 | $2,000.00 |
| 31 | 2050-19 DEMOLISH HPU HOUSE AND PLATFORM | 1.00 | LS |
1.00
| 0.95 | 0.05 | $155,000.00 | $7,750.00 |
| 42 | 2050-30 REMOVE EXISTING EMERGENCY GENERATOR AND 100 GALLON FUEL TANK | 1.00 | LS |
1.00
| 0.90 | 0.10 | $15,000.00 | $1,500.00 |
| 44 | 2140-2 IMPLEMENTATION OF CONTROL OF WATER PLAN | 1.00 | LS |
0.87
| 0.84 | 0.03 | $125,000.00 | $3,750.00 |
| 49 | 2200-8 EXCAVATION FOR SHOTCRETE REPAIRS (SPILLWAY IMPACT AREA) | 400.00 | SY |
400.00
| 380.00 | 20.00 | $95.00 | $1,900.00 |
| 55 | 2900-2 RELOCATE EXISTING STANDPIPE WEIR | 1.00 | LS |
0.20
| 0.00 | 0.20 | $10,000.00 | $2,000.00 |
| 57 | 3300-1 OGEE SPILLWAY | 1.00 | LS |
0.97
| 0.90 | 0.07 | $5,250,000.00 | $367,500.00 |
| 70 | 3361-2 SHOTCRETE REPAIRS (SPILLWAY IMPACT AREA) | 400.00 | SY |
400.00
| 380.00 | 20.00 | $750.00 | $15,000.00 |
| 92 | 14200-1 REMOVE, REHABILITATE, AND REINSTALL 5-TON JIB CRANE | 1.00 | LS |
0.50
| 0.15 | 0.35 | $250,000.00 | $87,500.00 |
| 101 | OUTLET 2 VALVES AND ALL APPURTENANT WORK | 1.00 | LS |
0.95
| 0.46 | 0.49 | $250,000.00 | $122,500.00 |
| 102 | OUTLET 3 VALVES AND ALL APPURTENANT WORK | 1.00 | LS |
0.95
| 0.90 | 0.05 | $250,000.00 | $12,500.00 |
| 103 | OUTLET 4 VALVES AND ALL APPURTENANT WORK | 1.00 | LS |
0.95
| 0.90 | 0.05 | $250,000.00 | $12,500.00 |
| 114 | CHANGEABLE MESSAGE SIGN (EACH) | 60.00 | MTH |
58.00
| 56.00 | 2.00 | $1,000.00 | $2,000.00 |
| S-29A | ACCESS ROAD REPAIRS | | T&M |
867,761.00
| 789,645.00 | 78,116.00 | $1.00 | $78,116.00 |
| S-31 | VALVE HOUSE METAL PANEL COATING | | LS |
1.00
| 0.00 | 1.00 | $14,000.00 | $14,000.00 |
| S-45 | RETAINING WALL AT OLD GARAGE AREA | | LS |
1.00
| 0.00 | 1.00 | $21,500.00 | $21,500.00 |
| S-55 | LEAD PAINT ABATEMENT AND ASBESTOS REMOVAL AT CONTROL HOUSE | | LS |
1.00
| 0.00 | 1.00 | $36,500.00 | $36,500.00 |
| S-61 | GENERATOR USAGE BEFORE ENERGIZING | | LS |
1.00
| 0.00 | 1.00 | $47,400.00 | $47,400.00 |
|