| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $750/MONTH) | 30.00 | MTH |
32.00
| 31.00 | 1.00 | $750.00 | $750.00 |
| 5 | UST CLOSURE REPORT (STIPULATED UNIT PRICE OF $2,500) | 1.00 | LS |
1.00
| 0.50 | 0.50 | $2,500.00 | $1,250.00 |
| 7 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.87
| 0.85 | 0.02 | $170,000.00 | $3,400.00 |
| 9 | REMOVAL AND DISPOSAL OF LBP/LCP AND ACM DEBRIS | 1.00 | LS |
0.95
| 0.90 | 0.05 | $150,000.00 | $7,500.00 |
| 10 | IMPLEMENTATION OF THE ENVIRONMENTAL PLANS | 1.00 | LS |
0.80
| 0.77 | 0.03 | $50,000.00 | $1,500.00 |
| 11 | OFFICE FACILITIES | 30.00 | MTH |
31.00
| 30.00 | 1.00 | $4,000.00 | $4,000.00 |
| 20 | 2050-8 REMOVE LADDERS | 1.00 | LS |
1.00
| 0.70 | 0.30 | $25,000.00 | $7,500.00 |
| 24 | 2050-12 REMOVE PARTIALLY EXPOSED WATERLINE | 1.00 | LS |
0.70
| 0.50 | 0.20 | $20,000.00 | $4,000.00 |
| 44 | 2140-2 IMPLEMENTATION OF CONTROL OF WATER PLAN | 1.00 | LS |
0.90
| 0.87 | 0.03 | $125,000.00 | $3,750.00 |
| 55 | 2900-2 RELOCATE EXISTING STANDPIPE WEIR | 1.00 | LS |
0.50
| 0.20 | 0.30 | $10,000.00 | $3,000.00 |
| 57 | 3300-1 OGEE SPILLWAY | 1.00 | LS |
1.00
| 0.97 | 0.03 | $5,250,000.00 | $157,500.00 |
| 78 | 5500-9 DAM CREST HANDRAIL | 300.00 | LF |
300.00
| 200.00 | 100.00 | $200.00 | $20,000.00 |
| 80 | 5500-11 SHIP'S LADDER PLATFORMS AND WALKWAYS (UPSTREAM) | 1.00 | LS |
0.80
| 0.65 | 0.15 | $380,000.00 | $57,000.00 |
| 84 | 11290-1 RELOCATE HPU TO CONTROL HOUSE AND APPURTENANT WORK | 1.00 | LS |
0.70
| 0.60 | 0.10 | $150,000.00 | $15,000.00 |
| 88 | 13100-5 METAL POST GUARDRAIL (AT ENTRANCE GATE) | 1.00 | LS |
1.00
| 0.95 | 0.05 | $25,000.00 | $1,250.00 |
| 91 | 14100-2 HOIST HEAD TOWER, TAIL TOWER, AND SYSTEM REHABILITATION | 1.00 | LS |
0.45
| 0.15 | 0.30 | $100,000.00 | $30,000.00 |
| 97 | 16110-1 WATER LEVEL DATA LOGGER CONDUIT | 1.00 | LS |
0.20
| 0.00 | 0.20 | $5,000.00 | $1,000.00 |
| 106 | CONTROL BUILDING IMPROVEMENTS | 1.00 | LS |
0.60
| 0.40 | 0.20 | $100,000.00 | $20,000.00 |
| 107 | ELECTRICAL AND INSTRUMENTATION WORK | 1.00 | LS |
0.85
| 0.80 | 0.05 | $2,000,000.00 | $100,000.00 |
| 113 | SECTION R - CONCRETE SWALE (ROAD) | 249.00 | LF |
50.00
| 0.00 | 50.00 | $75.00 | $3,750.00 |
| 114 | CHANGEABLE MESSAGE SIGN (EACH) | 60.00 | MTH |
60.00
| 58.00 | 2.00 | $1,000.00 | $2,000.00 |
| 117 | 13100-7 RAIL LADDER FALL PROTECTION SYSTEMS | 1.00 | LS |
0.50
| 0.20 | 0.30 | $100,000.00 | $30,000.00 |
| S-26C | ADD NEW BEAM TO HEAD TOWER | | LS |
0.40
| 0.00 | 0.40 | $25,000.00 | $10,000.00 |
| S-26D | CABLE HOIST LIMIT SWITCH | | LS |
1.00
| 0.00 | 1.00 | $19,992.00 | $19,992.00 |
| S-26E | HOIST BUILDING MODIFICATION | | LS |
0.30
| 0.00 | 0.30 | $49,992.00 | $14,997.60 |
| S-29A | ACCESS ROAD REPAIRS | | T&M |
962,996.00
| 867,761.00 | 95,235.00 | $1.00 | $95,235.00 |
| S-29C | CMB, PLACED ON SAD POOL ROAD | | CY |
1,351.00
| 1,300.00 | 51.00 | $273.09 | $13,927.59 |
| S-29I | VERIFICATION TESTING | | T&M |
100,000.00
| 0.00 | 100,000.00 | $1.00 | $100,000.00 |
| S-42 | BMPS ALONG THE POOL ROAD | | T&M |
35,068.79
| 0.00 | 35,068.79 | $1.00 | $35,068.79 |
| S-57A | POUR 5 CANCELLATION | | LS |
1.00
| 0.00 | 1.00 | $30,430.00 | $30,430.00 |
| S-60 | 2" CONDUIT FOR FO CABLE | | LS |
0.50
| 0.00 | 0.50 | $18,500.00 | $9,250.00 |
| S-62 | RELOCATE OUTLET #4 DISCONNECTS | | LS |
1.00
| 0.00 | 1.00 | $8,630.00 | $8,630.00 |
| S-63 | COVER HANDRAIL AND SECURE AIRLINE | | LS |
0.50
| 0.00 | 0.50 | $5,000.00 | $2,500.00 |
|