| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $750/MONTH) | 30.00 | MTH |
33.00
| 32.00 | 1.00 | $750.00 | $750.00 |
| 7 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.89
| 0.87 | 0.02 | $170,000.00 | $3,400.00 |
| 9 | REMOVAL AND DISPOSAL OF LBP/LCP AND ACM DEBRIS | 1.00 | LS |
0.98
| 0.95 | 0.03 | $150,000.00 | $4,500.00 |
| 10 | IMPLEMENTATION OF THE ENVIRONMENTAL PLANS | 1.00 | LS |
0.90
| 0.80 | 0.10 | $50,000.00 | $5,000.00 |
| 11 | OFFICE FACILITIES | 30.00 | MTH |
32.00
| 31.00 | 1.00 | $4,000.00 | $4,000.00 |
| 44 | 2140-2 IMPLEMENTATION OF CONTROL OF WATER PLAN | 1.00 | LS |
0.92
| 0.90 | 0.02 | $125,000.00 | $2,500.00 |
| 80 | 5500-11 SHIP'S LADDER PLATFORMS AND WALKWAYS (UPSTREAM) | 1.00 | LS |
0.90
| 0.80 | 0.10 | $380,000.00 | $38,000.00 |
| 87 | 13100-4 WIND CONES | 2.00 | EA |
0.50
| 0.00 | 0.50 | $5,000.00 | $2,500.00 |
| 91 | 14100-2 HOIST HEAD TOWER, TAIL TOWER, AND SYSTEM REHABILITATION | 1.00 | LS |
0.60
| 0.45 | 0.15 | $100,000.00 | $15,000.00 |
| 100 | VALVE HOUSE IMPROVEMENTS | 1.00 | LS |
0.20
| 0.10 | 0.10 | $125,000.00 | $12,500.00 |
| 106 | CONTROL BUILDING IMPROVEMENTS | 1.00 | LS |
0.75
| 0.60 | 0.15 | $100,000.00 | $15,000.00 |
| 107 | ELECTRICAL AND INSTRUMENTATION WORK | 1.00 | LS |
0.87
| 0.85 | 0.02 | $2,000,000.00 | $40,000.00 |
| 113 | SECTION R - CONCRETE SWALE (ROAD) | 249.00 | LF |
103.00
| 50.00 | 53.00 | $75.00 | $3,975.00 |
| 114 | CHANGEABLE MESSAGE SIGN (EACH) | 60.00 | MTH |
62.00
| 60.00 | 2.00 | $1,000.00 | $2,000.00 |
| S-18 | LEAD PAINT REMOVAL VALVE HOUSE #3 | | LS |
1.00
| 0.60 | 0.40 | $40,000.00 | $16,000.00 |
| S-26E | HOIST BUILDING MODIFICATION | | LS |
0.50
| 0.30 | 0.20 | $49,992.00 | $9,998.40 |
| S-29A | ACCESS ROAD REPAIRS | | T&M |
1,036,866.00
| 962,996.00 | 73,870.00 | $1.00 | $73,870.00 |
| S-29I | VERIFICATION TESTING | | T&M |
157,447.00
| 100,000.00 | 57,447.00 | $1.00 | $57,447.00 |
| S-64 | REPLACE HOIST BUILDING CURB | | LS |
0.20
| 0.00 | 0.20 | $24,500.00 | $4,900.00 |
| S-66 | OBSTRUCTION LIGHT MOUNTING | | LS |
0.20
| 0.00 | 0.20 | $14,000.00 | $2,800.00 |
|