Los Angeles County Public Works
Project Management Division III
Progress Payment 1
Project Name: Workman Mill Road Landscaping
Contractor: Yakar
689 East San Bernardino Road
Covina, CA 91723
Project ID: RDC0016340
Federal Number(s): None
Original Contract: $921,209.50
Awarded: 7/28/2020
Period Ending: 11/20/2020
Board Accepted: 11/8/2021
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
1CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $5,000)1.00LS 1.00 0.001.00$5,000.00$5,000.00
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $750/MONTH)3.00MTH 1.00 0.001.00$750.00$750.00
4IMPLEMENTATION OF BMPS1.00LS 0.33 0.000.33$5,000.00$1,650.00
5OFFICE FACILITIES3.00MTH 1.00 0.001.00$1,500.00$1,500.00
6MOBILIZATION1.00LS 0.95 0.000.95$47,500.00$45,125.00
7CLEARING AND GRUBBING1.00LS 0.33 0.000.33$27,500.00$9,075.00
8CONCRETE REMOVAL (NON-REINFORCED)86.00CY 75.00 0.0075.00$265.00$19,875.00
9UNCLASSIFIED EXCAVATION595.00CY 400.00 0.00400.00$105.00$42,000.00
11TRAFFIC CONTROL1.00LS 0.33 0.000.33$15,000.00$4,950.00
12FLASHING ARROW SIGN2.00EA 1.00 0.001.00$1,500.00$1,500.00
14IRRIGATION SYSTEM1.00LS 0.25 0.000.25$255,000.00$63,750.00
17WELDED WIRE VINE TRELLIS3,915.00LF 1,000.00 0.001,000.00$69.00$69,000.00
19REMOVE EXISTING WOOD HEADER6,650.00LF 3,500.00 0.003,500.00$0.50$1,750.00
21AGRONOMIC SOIL REPORT6.00EA 1.00 0.001.00$100.00$100.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $266,025.00 $0.00 $266,025.00
Retained $13,301.25 $0.00 $13,301.25
Deducted $0.00 $0.00 $0.00
Due $252,723.75 $0.00 $252,723.75



Contact Office Engineer
Contractor Copy  