| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $750/MONTH) | 30.00 | MTH |
35.00
| 34.00 | 1.00 | $750.00 | $750.00 |
| 7 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.93
| 0.91 | 0.02 | $170,000.00 | $3,400.00 |
| 44 | 2140-2 IMPLEMENTATION OF CONTROL OF WATER PLAN | 1.00 | LS |
0.95
| 0.94 | 0.01 | $125,000.00 | $1,250.00 |
| 54 | 2900-1 WATER SYSTEM REPLACEMENT AND REHABILITATION | 1.00 | LS |
0.90
| 0.85 | 0.05 | $450,000.00 | $22,500.00 |
| 76 | 5500-7 REMOVABLE LOCKABLE BOLLARDS | 16.00 | EA |
8.00
| 0.00 | 8.00 | $1,000.00 | $8,000.00 |
| 87 | 13100-4 WIND CONES | 2.00 | EA |
1.50
| 0.50 | 1.00 | $5,000.00 | $5,000.00 |
| 91 | 14100-2 HOIST HEAD TOWER, TAIL TOWER, AND SYSTEM REHABILITATION | 1.00 | LS |
1.00
| 0.95 | 0.05 | $100,000.00 | $5,000.00 |
| 92 | 14200-1 REMOVE, REHABILITATE, AND REINSTALL 5-TON JIB CRANE | 1.00 | LS |
0.90
| 0.50 | 0.40 | $250,000.00 | $100,000.00 |
| 100 | VALVE HOUSE IMPROVEMENTS | 1.00 | LS |
0.50
| 0.20 | 0.30 | $125,000.00 | $37,500.00 |
| 114 | CHANGEABLE MESSAGE SIGN (EACH) | 60.00 | MTH |
66.00
| 64.00 | 2.00 | $1,000.00 | $2,000.00 |
| S-7 | MODIFY RETAINING WALL ANCHORS | | LS |
0.00
| 0.79 | -0.79 | $143,250.00 | ($113,167.50) |
| S-7A | MODIFY RETAINING WALL ANCHORS | | LS |
1.00
| 0.00 | 1.00 | $113,250.00 | $113,250.00 |
| S-26E | HOIST BUILDING MODIFICATION | | LS |
1.00
| 0.50 | 0.50 | $49,992.00 | $24,996.00 |
| S-29A | ACCESS ROAD REPAIRS | | T&M |
1,158,294.00
| 1,083,650.00 | 74,644.00 | $1.00 | $74,644.00 |
| S-29I | VERIFICATION TESTING | | T&M |
244,405.00
| 200,000.00 | 44,405.00 | $1.00 | $44,405.00 |
| S-39A | 4 INCH WATER LINE | | LS |
0.35
| 0.25 | 0.10 | $490,000.00 | $49,000.00 |
| S-59 | REPLACE TOE LIGHT WIRING | | LS |
1.00
| 0.00 | 1.00 | $13,300.00 | $13,300.00 |
| S-60 | 2" CONDUIT FOR FO CABLE | | LS |
1.00
| 0.50 | 0.50 | $18,500.00 | $9,250.00 |
| S-65 | RAMP BEHIND GENERATOR BUILDING | | LS |
1.00
| 0.20 | 0.80 | $105,000.00 | $84,000.00 |
| S-66 | OBSTRUCTION LIGHT MOUNTING | | LS |
1.00
| 0.50 | 0.50 | $14,000.00 | $7,000.00 |
| S-68 | OGEE SPILLWAY TIME RELATED IMPACTS | | LS |
1.00
| 0.00 | 1.00 | $53,250.00 | $53,250.00 |
| S-69 | MODIFY HANDRAIL AND CONDUIT AT PARAPET WALL | | LS |
1.00
| 0.00 | 1.00 | $6,500.00 | $6,500.00 |
| S-71 | ANCHOR WIND CONE | | LS |
1.00
| 0.00 | 1.00 | $1,650.00 | $1,650.00 |
|