| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $750/MONTH) | 30.00 | MTH |
38.00
| 37.00 | 1.00 | $750.00 | $750.00 |
| 7 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.97
| 0.96 | 0.01 | $170,000.00 | $1,700.00 |
| 11 | OFFICE FACILITIES | 30.00 | MTH |
37.00
| 36.00 | 1.00 | $4,000.00 | $4,000.00 |
| 44 | 2140-2 IMPLEMENTATION OF CONTROL OF WATER PLAN | 1.00 | LS |
0.98
| 0.97 | 0.01 | $125,000.00 | $1,250.00 |
| 79 | 5500-10 36"X30" INSTRUMENT ENCLOSURE WITH 1 1/2" DRAIN | 1.00 | LS |
0.50
| 0.25 | 0.25 | $20,000.00 | $5,000.00 |
| 92 | 14200-1 REMOVE, REHABILITATE, AND REINSTALL 5-TON JIB CRANE | 1.00 | LS |
1.00
| 0.98 | 0.02 | $250,000.00 | $5,000.00 |
| 93 | 15900-4 SLUICEWAY LINING | 1.00 | LS |
1.00
| 0.95 | 0.05 | $175,000.00 | $8,750.00 |
| 95 | 16050-7 RELOCATE ACCELEROMETER AND NEMA BOX | 1.00 | LS |
0.50
| 0.00 | 0.50 | $20,000.00 | $10,000.00 |
| 100 | VALVE HOUSE IMPROVEMENTS | 1.00 | LS |
0.90
| 0.80 | 0.10 | $125,000.00 | $12,500.00 |
| 107 | ELECTRICAL AND INSTRUMENTATION WORK | 1.00 | LS |
0.94
| 0.93 | 0.01 | $2,000,000.00 | $20,000.00 |
| 114 | CHANGEABLE MESSAGE SIGN (EACH) | 60.00 | MTH |
72.00
| 70.00 | 2.00 | $1,000.00 | $2,000.00 |
| S-29A | ACCESS ROAD REPAIRS | | T&M |
1,342,194.00
| 1,283,295.00 | 58,899.00 | $1.00 | $58,899.00 |
| S-29I | VERIFICATION TESTING | | T&M |
538,637.00
| 436,459.00 | 102,178.00 | $1.00 | $102,178.00 |
| S-32 | SURVEILLANCE SYSTEM (NEGOTIATED) | | LS |
0.85
| 0.75 | 0.10 | $47,735.00 | $4,773.50 |
| S-39A | 4 INCH WATER LINE | | LS |
0.60
| 0.50 | 0.10 | $490,000.00 | $49,000.00 |
| S-73 | MODIFY VALVE AIR VENTS | | LS |
0.75
| 0.60 | 0.15 | $24,000.00 | $3,600.00 |
| S-79 | WATER LINE REALIGNMENT | | LS |
0.75
| 0.00 | 0.75 | $90,000.00 | $67,500.00 |
|