| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $750/MONTH) | 30.00 | MTH |
40.00
| 39.00 | 1.00 | $750.00 | $750.00 |
| 7 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.99
| 0.98 | 0.01 | $170,000.00 | $1,700.00 |
| 11 | OFFICE FACILITIES | 30.00 | MTH |
39.00
| 38.00 | 1.00 | $4,000.00 | $4,000.00 |
| 44 | 2140-2 IMPLEMENTATION OF CONTROL OF WATER PLAN | 1.00 | LS |
0.99
| 0.98 | 0.01 | $125,000.00 | $1,250.00 |
| 54 | 2900-1 WATER SYSTEM REPLACEMENT AND REHABILITATION | 1.00 | LS |
0.94
| 0.92 | 0.02 | $450,000.00 | $9,000.00 |
| 73 | 5500-1 SHIP'S LADDER, PLATFORMS, AND WALKWAYS (DOWNSTREAM) | 1.00 | LS |
1.00
| 0.95 | 0.05 | $450,000.00 | $22,500.00 |
| 74 | 5500-2 SLUICEWAY DRAWBRIDGE | 1.00 | LS |
1.00
| 0.95 | 0.05 | $33,000.00 | $1,650.00 |
| 79 | 5500-10 36"X30" INSTRUMENT ENCLOSURE WITH 1 1/2" DRAIN | 1.00 | LS |
1.00
| 0.50 | 0.50 | $20,000.00 | $10,000.00 |
| 81 | 11010-1 QUALITY REQUIREMENTS FOR EQUIPMENT | 1.00 | LS |
0.75
| 0.50 | 0.25 | $5,000.00 | $1,250.00 |
| 82 | 11020-1 INSPECTIONS AND TESTS FOR EQUIPMENT | 1.00 | LS |
0.75
| 0.50 | 0.25 | $5,000.00 | $1,250.00 |
| 83 | 11040-1 MANUFACTURER'S SERVICES | 1.00 | LS |
0.75
| 0.50 | 0.25 | $3,000.00 | $750.00 |
| 100 | VALVE HOUSE IMPROVEMENTS | 1.00 | LS |
0.98
| 0.95 | 0.03 | $125,000.00 | $3,750.00 |
| 101 | OUTLET 2 VALVES AND ALL APPURTENANT WORK | 1.00 | LS |
0.95
| 0.90 | 0.05 | $250,000.00 | $12,500.00 |
| 102 | OUTLET 3 VALVES AND ALL APPURTENANT WORK | 1.00 | LS |
0.95
| 0.90 | 0.05 | $250,000.00 | $12,500.00 |
| 103 | OUTLET 4 VALVES AND ALL APPURTENANT WORK | 1.00 | LS |
0.95
| 0.90 | 0.05 | $250,000.00 | $12,500.00 |
| 104 | GENERATOR BUILDING (COMPLETE) | 1.00 | LS |
0.99
| 0.98 | 0.01 | $655,000.00 | $6,550.00 |
| 107 | ELECTRICAL AND INSTRUMENTATION WORK | 1.00 | LS |
0.97
| 0.95 | 0.02 | $2,000,000.00 | $40,000.00 |
| 114 | CHANGEABLE MESSAGE SIGN (EACH) | 60.00 | MTH |
76.00
| 74.00 | 2.00 | $1,000.00 | $2,000.00 |
| 117 | 13100-7 RAIL LADDER FALL PROTECTION SYSTEMS | 1.00 | LS |
0.90
| 0.85 | 0.05 | $100,000.00 | $5,000.00 |
| S-26G | HOIST FESTOON SYSTEM | | LS |
1.00
| 0.00 | 1.00 | $256,000.00 | $256,000.00 |
| S-29A | ACCESS ROAD REPAIRS | | T&M |
1,461,685.00
| 1,400,259.00 | 61,426.00 | $1.00 | $61,426.00 |
| S-38 | EXTEND LEAKAGE LINE AT EAST ARMORING | | LS |
1.00
| 0.50 | 0.50 | $6,360.00 | $3,180.00 |
| S-39A | 4 INCH WATER LINE | | LS |
0.80
| 0.75 | 0.05 | $490,000.00 | $24,500.00 |
| S-70 | INSTALL FLOOD LIGHTS AT HOIST BUILDING | | LS |
1.00
| 0.95 | 0.05 | $17,725.00 | $886.25 |
| S-72 | SAFETY CHAIN BARRIERS | | LS |
1.00
| 0.00 | 1.00 | $2,600.00 | $2,600.00 |
| S-79 | WATER LINE REALIGNMENT | | LS |
1.00
| 0.90 | 0.10 | $90,000.00 | $9,000.00 |
| S-80 | CONDUIT FOR INSTRUMENTATION | | LS |
1.00
| 0.30 | 0.70 | $45,000.00 | $31,500.00 |
| S-81 | VALVE HOUSE TELEPHONE CONDUIT | | LS |
1.00
| 0.50 | 0.50 | $16,320.00 | $8,160.00 |
| S-82 | HELIPORT SAFETY NETTING | | LS |
1.00
| 0.10 | 0.90 | $29,585.00 | $26,626.50 |
| S-83 | GABION WALL ALONG WATER LINE | | LS |
0.10
| 0.00 | 0.10 | $212,000.00 | $21,200.00 |
| S-85 | ADDITIONAL SUPPORTS AT S-38 & S-39 | | LS |
1.00
| 0.00 | 1.00 | $2,700.00 | $2,700.00 |
|