| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 9.00 | MTH |
10.00
| 9.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.745
| 0.66 | 0.085 | $25,000.00 | $2,125.00 |
| 6 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.91
| 0.88 | 0.03 | $35,000.00 | $1,050.00 |
| 9 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
0.82
| 0.76 | 0.06 | $25,000.00 | $1,500.00 |
| 10 | DISPOSAL OF CONTAMINATED SOIL, CLASS I LANDFILL | 45.00 | TON |
51.00
| 45.00 | 6.00 | $150.00 | $900.00 |
| 11 | EXCLUSIONARY FENCING | 50.00 | LF |
48.75
| 48.50 | 0.25 | $200.00 | $50.00 |
| 12 | SILT FENCE (SLOPE PROTECTION) | 1.00 | LS |
0.932
| 0.91 | 0.022 | $20,000.00 | $440.00 |
| 13 | OFFICE FACILITIES | 9.00 | MTH |
9.50
| 8.50 | 1.00 | $2,500.00 | $2,500.00 |
| 18 | CLEARING AND GRUBBING | 1.00 | LS |
0.77
| 0.75 | 0.02 | $250,000.00 | $5,000.00 |
| 31 | STRUCTURE EXCAVATION (BRIDGE) | 257.00 | CY |
124.25
| 64.25 | 60.00 | $100.00 | $6,000.00 |
| 33 | STRUCTURE BACKFILL (BRIDGE) | 150.00 | CY |
45.00
| 30.00 | 15.00 | $50.00 | $750.00 |
| 38 | STRUCTURE CONCRETE (BRIDGE) | 452.00 | CY |
171.00
| 36.00 | 135.00 | $1,250.00 | $168,750.00 |
| 40 | TEMPORARY FALSEWORK | 1.00 | LS |
0.52
| 0.40 | 0.12 | $35,000.00 | $4,200.00 |
| 44 | ELASTOMERIC BEARING PAD | 202.00 | EA |
119.00
| 69.00 | 50.00 | $200.00 | $10,000.00 |
| 45 | BAR REINFORCING STEEL (BRIDGE) | 139,000.00 | LB |
90,961.40
| 50,111.00 | 40,850.40 | $1.25 | $51,063.00 |
| 50 | REINFORCED CONCRETE STAIRWAY PER STD PLAN 640 | 3.00 | CY |
3.50
| 3.00 | 0.50 | $1,500.00 | $750.00 |
| 54 | AIR-PLACED CONCRETE, 3" | 28.00 | SY |
64.00
| 62.26 | 1.74 | $625.00 | $1,087.50 |
| 55 | AIR-PLACED CONCRETE, 6" | 261.00 | SY |
197.00
| 181.00 | 16.00 | $625.00 | $10,000.00 |
| 59 | METAL HAND RAILINGS PER STD PLAN 606 | 37.00 | LF |
50.00
| 37.00 | 13.00 | $122.00 | $1,586.00 |
| 60 | CABLE RAILING (CALTRANS STD PLAN B11-47) (MODIFIED) | 400.00 | LF |
40.00
| 0.00 | 40.00 | $63.80 | $2,552.00 |
| 61 | CHAIN LINK FENCE, 4' HIGH | 45.00 | LF |
48.00
| 45.00 | 3.00 | $62.00 | $186.00 |
| 67 | 24" DIA CIDH PILES | 108.00 | LF |
98.00
| 48.48 | 49.52 | $300.00 | $14,856.00 |
| 68 | 36" DIA CIDH PILES | 422.00 | LF |
422.00
| 369.70 | 52.30 | $450.00 | $23,535.00 |
| S-18 | ADDITIONAL TIMBER RAILING REMOVAL | | LS |
0.30
| 0.00 | 0.30 | $11,000.00 | $3,300.00 |