| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 1 | CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $5,000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $5,000.00 | $5,000.00 |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 5.00 | MTH |
1.00
| 0.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.20
| 0.00 | 0.20 | $5,500.00 | $1,100.00 |
| 5 | PREPARATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN (STIPULATED UNIT PRICE OF $3000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $3,000.00 | $3,000.00 |
| 6 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
0.20
| 0.00 | 0.20 | $5,000.00 | $1,000.00 |
| 7 | PREPARATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN (STIPULATED UNIT PRICE OF $3000) | 1.00 | LS |
1.00
| 0.00 | 1.00 | $3,000.00 | $3,000.00 |
| 11 | OFFICE FACILITIES | 6.00 | MTH |
2.00
| 0.00 | 2.00 | $1,000.00 | $2,000.00 |
| 12 | MOBILIZATION | 1.00 | LS |
0.95
| 0.00 | 0.95 | $171,000.00 | $162,450.00 |
| 13 | TEMPORARY WATER BARRIERS | 1.00 | LS |
0.66
| 0.00 | 0.66 | $120,000.00 | $79,200.00 |
| 15 | MISCELLANEOUS MECHANICAL WORK | 1.00 | LS |
0.09
| 0.00 | 0.09 | $244,000.00 | $21,960.00 |
| 16 | 24" VERTICAL AXIAL FLOW PROPELLER PUMP WITH ELECTRIC MOTOR | 2.00 | EA |
1.00
| 0.00 | 1.00 | $183,500.00 | $183,500.00 |
| 18 | DISCHARGE LINES REPLACEMENT AND REHABILITATION | 1.00 | LS |
0.25
| 0.00 | 0.25 | $233,000.00 | $58,250.00 |
| 21 | FIBERGLASS REINFORCED POLYMER PLATFORM | 1.00 | LS |
0.62
| 0.00 | 0.62 | $40,000.00 | $24,800.00 |