Los Angeles County Public Works
Project Management Division III
Progress Payment 1
Project Name: Los Altos Pumping Plant Mechanical and Electrical Rehabilitation
Contractor: Kiewit Infrastructure West Company
10704 Shoemaker Avenue
Santa Fe Springs, CA 90670-4024
Project ID: FCC0001334
Federal Number(s): None
Original Contract: $1,851,000.00
Awarded: 9/29/2020
Period Ending: 7/6/2021
Board Accepted: 11/30/2021
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
1CONSTRUCTION SCHEDULE (BASELINE) (STIPULATED UNIT PRICE OF $5,000)1.00LS 1.00 0.001.00$5,000.00$5,000.00
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)5.00MTH 1.00 0.001.00$500.00$500.00
4IMPLEMENTATION OF THE LTWHP1.00LS 0.20 0.000.20$5,500.00$1,100.00
5PREPARATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN (STIPULATED UNIT PRICE OF $3000)1.00LS 1.00 0.001.00$3,000.00$3,000.00
6IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN 1.00LS 0.20 0.000.20$5,000.00$1,000.00
7PREPARATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN (STIPULATED UNIT PRICE OF $3000)1.00LS 1.00 0.001.00$3,000.00$3,000.00
11OFFICE FACILITIES6.00MTH 2.00 0.002.00$1,000.00$2,000.00
12MOBILIZATION1.00LS 0.95 0.000.95$171,000.00$162,450.00
13TEMPORARY WATER BARRIERS1.00LS 0.66 0.000.66$120,000.00$79,200.00
15MISCELLANEOUS MECHANICAL WORK1.00LS 0.09 0.000.09$244,000.00$21,960.00
1624" VERTICAL AXIAL FLOW PROPELLER PUMP WITH ELECTRIC MOTOR2.00EA 1.00 0.001.00$183,500.00$183,500.00
18DISCHARGE LINES REPLACEMENT AND REHABILITATION1.00LS 0.25 0.000.25$233,000.00$58,250.00
21FIBERGLASS REINFORCED POLYMER PLATFORM1.00LS 0.62 0.000.62$40,000.00$24,800.00

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $545,760.00 $0.00 $545,760.00
Retained $27,288.00 $0.00 $27,288.00
Deducted $0.00 $0.00 $0.00
Due $518,472.00 $0.00 $518,472.00



Contact Office Engineer
Chandra McLoud (626) 458-3165