| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 7 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
1.00
| 0.99 | 0.01 | $170,000.00 | $1,700.00 |
| 100 | VALVE HOUSE IMPROVEMENTS | 1.00 | LS |
1.00
| 0.99 | 0.01 | $125,000.00 | $1,250.00 |
| 106 | CONTROL BUILDING IMPROVEMENTS | 1.00 | LS |
1.00
| 0.90 | 0.10 | $100,000.00 | $10,000.00 |
| 112 | SECTION R - PCC GUTTER (ROAD) | 878.00 | LF |
1,070.00
| 1,000.00 | 70.00 | $45.00 | $3,150.00 |
| 117 | 13100-7 RAIL LADDER FALL PROTECTION SYSTEMS | 1.00 | LS |
1.00
| 0.90 | 0.10 | $100,000.00 | $10,000.00 |
| S-29 | RAIL SYSTEM AND LIFELINE FOR ACCESS ROAD | | LS |
1.00
| 0.80 | 0.20 | $210,000.00 | $42,000.00 |
| S-29A | ACCESS ROAD REPAIRS | | T&M |
1,569,870.78
| 1,519,412.07 | 50,458.71 | $1.00 | $50,458.71 |
| S-39A | 4 INCH WATER LINE | | LS |
1.00
| 0.95 | 0.05 | $490,000.00 | $24,500.00 |
| S-43 | INSTALL TWO JOINT METER BOXES AT BRIDGE RAMP | | LS |
1.00
| 0.90 | 0.10 | $5,300.00 | $530.00 |
| S-83 | GABION WALL ALONG WATER LINE | | LS |
1.00
| 0.95 | 0.05 | $212,000.00 | $10,600.00 |
| S-86 | ACTUATORS WARRANTY EXTENSION | | YRS |
2.00
| 0.00 | 2.00 | $0.00 | $0.00 |
| S-89 | PLYWOOD FOR GABION WALL | | LS |
1.00
| 0.00 | 1.00 | $6,500.00 | $6,500.00 |