| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 5.00 | MTH |
2.00
| 1.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.40
| 0.20 | 0.20 | $5,500.00 | $1,100.00 |
| 6 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
0.40
| 0.20 | 0.20 | $5,000.00 | $1,000.00 |
| 8 | IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN | 1.00 | LS |
0.30
| 0.00 | 0.30 | $15,000.00 | $4,500.00 |
| 12 | MOBILIZATION | 1.00 | LS |
1.00
| 0.95 | 0.05 | $171,000.00 | $8,550.00 |
| 13 | TEMPORARY WATER BARRIERS | 1.00 | LS |
0.75
| 0.66 | 0.09 | $120,000.00 | $10,800.00 |
| 15 | MISCELLANEOUS MECHANICAL WORK | 1.00 | LS |
0.60
| 0.09 | 0.51 | $244,000.00 | $124,440.00 |
| 16 | 24" VERTICAL AXIAL FLOW PROPELLER PUMP WITH ELECTRIC MOTOR | 2.00 | EA |
1.50
| 1.00 | 0.50 | $183,500.00 | $91,750.00 |
| 17 | 36" VERTICAL AXIAL FLOW PROPELLER PUMP WITH RIGHT ANGLE GEAR DRIVE | 2.00 | EA |
0.25
| 0.00 | 0.25 | $211,000.00 | $52,750.00 |
| 18 | DISCHARGE LINES REPLACEMENT AND REHABILITATION | 1.00 | LS |
0.50
| 0.25 | 0.25 | $233,000.00 | $58,250.00 |
| 19 | FLAP GATES REFURBISHMENT | 1.00 | LS |
0.50
| 0.00 | 0.50 | $35,000.00 | $17,500.00 |
| 21 | FIBERGLASS REINFORCED POLYMER PLATFORM | 1.00 | LS |
0.90
| 0.62 | 0.28 | $40,000.00 | $11,200.00 |
| 22 | ELECTRICAL WORK | 1.00 | LS |
0.25
| 0.00 | 0.25 | $55,000.00 | $13,750.00 |
| S-1 | PUMP #3MODIFICATION | | LS |
0.9944
| 0.00 | 0.9944 | $10,000.00 | $9,944.00 |
| S-2 | $2" DRESSER COUPLING | | LS |
1.00
| 0.00 | 1.00 | $2,188.23 | $2,188.23 |
| S-3 | VICTAULIC COUPLING | | LS |
1.00
| 0.00 | 1.00 | $938.21 | $938.21 |
| S-4 | PLATFORM WALL BRACKET MODIFICATION | | LS |
1.00
| 0.00 | 1.00 | $17,850.00 | $17,850.00 |