| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 13.00 | MTH |
3.00
| 2.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.24
| 0.16 | 0.08 | $2,000.00 | $160.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.24
| 0.16 | 0.08 | $20,000.00 | $1,600.00 |
| 7 | SHORING OF OPEN EXCAVATIONS | 1.00 | LS |
0.24
| 0.16 | 0.08 | $3,110.00 | $248.80 |
| 9 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
0.24
| 0.16 | 0.08 | $5,000.00 | $400.00 |
| 12 | OFFICE FACILITIES | 13.00 | MTH |
3.00
| 2.00 | 1.00 | $2,000.00 | $2,000.00 |
| 14 | CLEARING AND GRUBBING | 1.00 | LS |
0.65
| 0.45 | 0.20 | $34,094.00 | $6,818.80 |
| 19 | UNCLASSIFIED EXCAVATION | 1,490.00 | CY |
135.00
| 0.00 | 135.00 | $45.00 | $6,075.00 |
| 32 | TRAFFIC CONTROL | 1.00 | LS |
0.31
| 0.23 | 0.08 | $90,300.00 | $7,224.00 |
| 41 | USE OF CONTRACTOR'S DRILL RIG | 190.00 | HR |
12.00
| 6.00 | 6.00 | $170.00 | $1,020.00 |
| 47 | IMPLEMENTATION OF THE GROUNDWATER MANAGEMENT PLAN | 1.00 | LS |
0.36
| 0.28 | 0.08 | $540,931.00 | $43,274.48 |
| 49 | NOISE CONTROL (ALLOWANCE OF 70,000) | 70,000.00 | AL |
34,065.00
| 21,089.00 | 12,976.00 | $1.00 | $12,976.00 |
| 53 | DRILL PILOT HOLE | 3,502.00 | VF |
1,516.00
| 791.00 | 725.00 | $479.00 | $347,275.00 |
| 57 | DRILL 42" DIAMETER BOREHOLE | 385.00 | VF |
245.00
| 175.00 | 70.00 | $670.00 | $46,900.00 |
| 59 | 36" DIAMETER PROTECTIVE STEEL CASING | 385.00 | VF |
245.00
| 175.00 | 70.00 | $285.00 | $19,950.00 |
| 63 | GROUT 42" DIAMETER BOREHOLE | 385.00 | VF |
195.00
| 175.00 | 20.00 | $200.00 | $4,000.00 |
| 67 | PRECAST INJECTION WELL VAULT | 11.00 | EA |
1.00
| 0.00 | 1.00 | $36,000.00 | $36,000.00 |
| 78 | PRIMARY WELL DEVELOPMENT WITH SWABBING AND AIRLIFTING | 550.00 | HR |
47.00
| 20.00 | 27.00 | $542.00 | $14,634.00 |
| 84 | 14" STEEL PIPE SCH 30, CML & CMC | 69.00 | LF |
69.00
| 66.00 | 3.00 | $391.00 | $1,173.00 |
| S-2 | INSTALL GREEN SHEETING, REPAIR, AND MAINTENANCE | | T&M |
3,816.00
| 0.00 | 3,816.00 | $1.00 | $3,816.00 |