| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 5.00 | MTH |
4.00
| 3.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.80
| 0.60 | 0.20 | $5,500.00 | $1,100.00 |
| 6 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
0.80
| 0.60 | 0.20 | $5,000.00 | $1,000.00 |
| 9 | REMOVAL AND DISPOSAL OF LBP/LCP | 1.00 | LS |
1.00
| 0.00 | 1.00 | $51,000.00 | $51,000.00 |
| 11 | OFFICE FACILITIES | 6.00 | MTH |
4.00
| 3.00 | 1.00 | $1,000.00 | $1,000.00 |
| 13 | TEMPORARY WATER BARRIERS | 1.00 | LS |
1.00
| 0.95 | 0.05 | $120,000.00 | $6,000.00 |
| 17 | 36" VERTICAL AXIAL FLOW PROPELLER PUMP WITH RIGHT ANGLE GEAR DRIVE | 2.00 | EA |
2.00
| 0.50 | 1.50 | $211,000.00 | $316,500.00 |
| 18 | DISCHARGE LINES REPLACEMENT AND REHABILITATION | 1.00 | LS |
1.00
| 0.75 | 0.25 | $233,000.00 | $58,250.00 |
| 19 | FLAP GATES REFURBISHMENT | 1.00 | LS |
1.00
| 0.75 | 0.25 | $35,000.00 | $8,750.00 |
| 20 | CONCRETE COLLAR SUPPORTS | 1.00 | LS |
1.00
| 0.50 | 0.50 | $60,000.00 | $30,000.00 |
| 22 | ELECTRICAL WORK | 1.00 | LS |
1.00
| 0.50 | 0.50 | $55,000.00 | $27,500.00 |
| S-5 | PIPE SUPPORT DISCHARGE LINE 3 | | LS |
1.00
| 0.00 | 1.00 | $1,300.00 | $1,300.00 |
| S-6 | DISCHARGE PIPE COATING | | LS |
1.00
| 0.00 | 1.00 | $4,700.00 | $4,700.00 |
| S-7 | EXPLOSION PROOF SWITCH | | LS |
1.00
| 0.00 | 1.00 | $1,600.00 | $1,600.00 |
| S-8 | SOLID CONTAINMENT WALL (COFFERDAM) | | LS |
1.00
| 0.00 | 1.00 | $8,300.00 | $8,300.00 |
| S-9 | WET WELL CONCRETE REPAIR | | LS |
1.00
| 0.00 | 1.00 | $5,800.00 | $5,800.00 |
| S-10 | DISCHARGE LINE SLEEVES | | LS |
1.00
| 0.00 | 1.00 | $16,000.00 | $16,000.00 |
| S-11 | CONTRACT TIME EXTENSION | | WD |
12.00
| 0.00 | 12.00 | $0.00 | $0.00 |
|