| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 13.00 | MTH |
5.00
| 4.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.40
| 0.32 | 0.08 | $2,000.00 | $160.00 |
| 5 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.40
| 0.32 | 0.08 | $20,000.00 | $1,600.00 |
| 6 | RESTORATION OF EXISTING IMPROVEMENTS | 1.00 | LS |
0.08
| 0.00 | 0.08 | $72,300.00 | $5,784.00 |
| 7 | SHORING OF OPEN EXCAVATIONS | 1.00 | LS |
0.40
| 0.32 | 0.08 | $3,110.00 | $248.80 |
| 9 | IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN | 1.00 | LS |
0.40
| 0.32 | 0.08 | $5,000.00 | $400.00 |
| 12 | OFFICE FACILITIES | 13.00 | MTH |
5.00
| 4.00 | 1.00 | $2,000.00 | $2,000.00 |
| 13 | MOBILIZATION | 1.00 | LS |
0.95
| 0.75 | 0.20 | $960,602.00 | $192,120.40 |
| 19 | UNCLASSIFIED EXCAVATION | 1,490.00 | CY |
405.00
| 135.00 | 270.00 | $45.00 | $12,150.00 |
| 20 | CRUSHED AGGREGATE BASE | 590.00 | CY |
197.00
| 98.00 | 99.00 | $106.00 | $10,494.00 |
| 29 | RESTORATION OF PERMANENT SURFACING | 1.00 | LS |
0.33
| 0.00 | 0.33 | $130,900.00 | $43,197.00 |
| 32 | TRAFFIC CONTROL | 1.00 | LS |
0.47
| 0.39 | 0.08 | $90,300.00 | $7,224.00 |
| 37 | 12" DIAM BLANK STAINLESS STEEL CASING | 1,469.00 | VF |
786.00
| 511.00 | 275.00 | $357.00 | $98,175.00 |
| 39 | GRAVEL PACK 24" DIAM HOLE | 1,595.00 | VF |
793.00
| 522.00 | 271.00 | $161.00 | $43,631.00 |
| 41 | USE OF CONTRACTOR'S DRILL RIG | 190.00 | HR |
15.00
| 13.00 | 2.00 | $170.00 | $340.00 |
| 47 | IMPLEMENTATION OF THE GROUNDWATER MANAGEMENT PLAN | 1.00 | LS |
0.52
| 0.44 | 0.08 | $540,931.00 | $43,274.48 |
| 49 | NOISE CONTROL (ALLOWANCE OF 70,000) | 70,000.00 | AL |
58,545.00
| 48,532.00 | 10,013.00 | $1.00 | $10,013.00 |
| 53 | DRILL PILOT HOLE | 3,502.00 | VF |
1,746.00
| 1,516.00 | 230.00 | $479.00 | $110,170.00 |
| 55 | DRILL 24" DIAMETER BOREHOLE | 1,805.00 | VF |
852.00
| 707.00 | 145.00 | $316.00 | $45,820.00 |
| 56 | DRILL 30" DIAMETER BOREHOLE | 1,029.00 | VF |
508.00
| 433.00 | 75.00 | $320.00 | $24,000.00 |
| 62 | GROUT 30" DIAMETER BOREHOLE | 1,006.00 | VF |
723.00
| 477.00 | 246.00 | $129.00 | $31,734.00 |
| 65 | SAND FILTER PACK FOR 30" DIAMETER BOREHOLE | 22.00 | VF |
12.00
| 8.00 | 4.00 | $111.00 | $444.00 |
| 67 | PRECAST INJECTION WELL VAULT | 11.00 | EA |
3.00
| 1.00 | 2.00 | $36,000.00 | $72,000.00 |
| 68 | INJECTION WELL HEAD ASSEMBLY | 11.00 | EA |
2.00
| 1.00 | 1.00 | $16,350.00 | $16,350.00 |
| 70 | WELL BOTTOM CAP (BULL NOSE) | 11.00 | EA |
5.00
| 4.00 | 1.00 | $904.00 | $904.00 |
| 71 | 12" DIAMETER STAINLESS STEEL SCREEN CASING | 1,495.00 | VF |
680.00
| 450.00 | 230.00 | $184.00 | $42,320.00 |
| 74 | 3" DIAMETER TREMIE PIPE SCHEDULE 80 PVC | 2,846.00 | VF |
1,386.00
| 906.00 | 480.00 | $9.00 | $4,320.00 |
| 76 | 4-INCH DIAMETER STAINLESS STEEL PIPE | 142.00 | LF |
26.00
| 13.00 | 13.00 | $360.00 | $4,680.00 |
| 77 | 6-INCH DIAMETER STAINLESS STEEL PIPE | 341.00 | LF |
76.00
| 38.00 | 38.00 | $446.00 | $16,948.00 |
| 78 | PRIMARY WELL DEVELOPMENT WITH SWABBING AND AIRLIFTING | 550.00 | HR |
111.50
| 61.50 | 50.00 | $542.00 | $27,100.00 |
| 79 | SECONDARY WELL DEVELOPMENT WITH HIGH VELOCITY WATER JETTING AND PUMPING | 800.00 | HR |
6.00
| 2.00 | 4.00 | $542.00 | $2,168.00 |
| 80 | ELECTRICAL WORK | 1.00 | LS |
0.39
| 0.25 | 0.14 | $751,723.00 | $105,241.22 |
| 81 | FIELD INSTRUMENTS | 1.00 | LS |
0.66
| 0.34 | 0.32 | $241,320.00 | $77,222.40 |
| 82 | SYSTEM INTEGRATION | 1.00 | LS |
0.64
| 0.00 | 0.64 | $152,215.00 | $97,417.60 |
| 87 | PCC EDGING | 1,474.00 | LF |
644.00
| 0.00 | 644.00 | $54.00 | $34,776.00 |
| 88 | PERMEABLE PAVERS | 10,650.00 | SF |
1,155.00
| 0.00 | 1,155.00 | $15.00 | $17,325.00 |
| 89 | PLAYGROUND CHIP MATERIAL | 102.00 | CY |
18.00
| 0.00 | 18.00 | $430.00 | $7,740.00 |
| 90 | REMOVABLE, LOCKABLE BOLLARDS | 21.00 | EA |
3.00
| 0.00 | 3.00 | $1,500.00 | $4,500.00 |
| S-3 | INJECTION WELL DRAIN CONNECTION | | LS |
1.00
| 0.00 | 1.00 | $7,000.00 | $7,000.00 |
|