| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 3.00 | MTH |
2.00
| 1.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.50
| 0.25 | 0.25 | $5,000.00 | $1,250.00 |
| 5 | OFFICE FACILITIES | 4.00 | MTH |
2.00
| 1.00 | 1.00 | $1,000.00 | $1,000.00 |
| 6 | MOBILIZATION | 1.00 | LS |
1.00
| 0.95 | 0.05 | $80,000.00 | $4,000.00 |
| 7 | TRAFFIC CONTROL | 1.00 | LS |
0.50
| 0.25 | 0.25 | $20,000.00 | $5,000.00 |
| 10 | UNCLASSIFIED EXCAVATION | 78.00 | CY |
78.00
| 0.00 | 78.00 | $200.00 | $15,600.00 |
| 12 | STRUCTURE EXCAVATION (RETAINING WALL) | 167.00 | CY |
167.00
| 0.00 | 167.00 | $250.00 | $41,750.00 |
| 13 | STRUCTURE BACKFILL (RETAINING WALL) | 34.00 | CY |
20.00
| 0.00 | 20.00 | $300.00 | $6,000.00 |
| 14 | NO. 3 CONCRETE AGGREGATE | 6.00 | CY |
5.00
| 0.00 | 5.00 | $350.00 | $1,750.00 |
| 15 | TRENCH BACKFILL SLURRY (CLASS 100-E-100) | 52.00 | CY |
52.00
| 0.00 | 52.00 | $150.00 | $7,800.00 |
| 18 | BAR REINFORCING STEEL | 8,000.00 | LB |
6,000.00
| 0.00 | 6,000.00 | $5.00 | $30,000.00 |
| 20 | CONST & REMOVE TEMP CHAIN LINK FENCE | 160.00 | LF |
80.00
| 0.00 | 80.00 | $80.00 | $6,400.00 |
| 21 | STRUCTURE CONCRETE (CIDH PILES) | 90.00 | CY |
90.00
| 27.00 | 63.00 | $490.00 | $30,870.00 |
| 22 | INSTALL STEEL PILE | 11.00 | EA |
11.00
| 4.00 | 7.00 | $1,200.00 | $8,400.00 |
| 23 | DRILL PILE HOLES, 36" DIA | 561.00 | LF |
470.00
| 306.50 | 163.50 | $98.00 | $16,023.00 |
| 26 | PREFABRICATED DRAINAGE COMPOSITE | 960.00 | SF |
960.00
| 0.00 | 960.00 | $14.00 | $13,440.00 |
| 27 | TIMBER LAGGING | 7.00 | MBF |
7.00
| 0.00 | 7.00 | $3,500.00 | $24,500.00 |
| 29 | NON-WOVEN GEOTEXTILE FABRIC | 65.00 | SY |
60.00
| 0.00 | 60.00 | $58.00 | $3,480.00 |
| 30 | 6" DIAMETER PVC PIPE, SCH 80 | 125.00 | LF |
125.00
| 0.00 | 125.00 | $78.00 | $9,750.00 |