Los Angeles County Public Works
Project Management Division III
Progress Payment 3
Project Name: Pacoima Spreading Grounds Basin Enhancement Project
Contractor: AMES CONSTRUCTION INC
2500 County Road 42 West
Burnsville , MN 55337
Project ID: FCC0001207
Federal Number(s): None
Original Contract: $54,483,460.00
Awarded: 5/6/2021
Period Ending: 10/20/2021
Board Accepted: 6/10/2025
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)34.00MTH 1.00 0.001.00$500.00$500.00
4IMPLEMENTATION OF THE LTWHP1.00LS 0.03 0.000.03$115,000.00$3,450.00
6IMPLEMENTATION OF THE SWPPP1.00LS 0.03 0.000.03$300,000.00$9,000.00
9IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN1.00LS 0.75 0.000.75$75,000.00$56,250.00
12IMPLEMENTATION OF THE FUGITIVE DUST CONTROL PLAN34.00MTH 1.00 0.001.00$8,000.00$8,000.00
15VEHICLES AND EQUIPMENT EMISSIONS REPORTING34.00MTH 1.00 0.001.00$8,000.00$8,000.00
18NOISE MONITORING AND REPORTING34.00MTH 1.00 0.001.00$6,000.00$6,000.00
20IMPLEMENTATION OF THE QUALITY CONTROL PROGRAM FOR MOISTURE CONTENT682.00DAY 3.00 0.003.00$1,000.00$3,000.00
22OFFICE FACILITIES34.00MTH 1.00 0.001.00$5,000.00$5,000.00
23MOBILIZATION1.00LS 0.50 0.000.50$3,998,042.48$1,999,021.24
24INSTALLATION OF TIRE WASHES3.00EA 2.00 0.002.00$115,000.00$230,000.00
25MAINTENANCE OF TIRE WASHES90.00MTH 1.00 0.001.00$3,500.00$3,500.00
26WATER TRUCKS682.00DAY 20.00 0.0020.00$1,500.00$30,000.00
27STREET SWEEPING682.00DAYS 16.00 0.0016.00$1,500.00$24,000.00
28PORTABLE SCALES3.00EA 2.00 0.002.00$180,000.00$360,000.00
29CONSTRUCTION OF TEMPORARY SOUND BARRIER5,800.00LF 5,623.00 0.005,623.00$210.00$1,180,830.00
30MAINTENANCE OF TEMPORARY SOUND BARRIER5,800.00LF 171.00 0.00171.00$23.00$3,933.00
32CLEARING AND GRUBBING1.00LS 0.33 0.000.33$150,000.00$49,500.00
38TREE REMOVAL (6"-12" DIAMETER)2.00EA 2.00 0.002.00$600.00$1,200.00
39TREE REMOVAL (13"-24" DIAMETER)8.00EA 8.00 0.008.00$1,200.00$9,600.00
40TREE REMOVAL (25"+ DIAMETER)11.00EA 11.00 0.0011.00$2,500.00$27,500.00
43CONCRETE REMOVAL (REINFORCED)523.00CY 268.00 0.00268.00$80.00$21,440.00
49EXCAVATION, TRANSPORTATION AND DISPOSAL OF EXCESS BASIN MATERIAL1,343,403.00CY 7,903.00 0.007,903.00$15.00$118,545.00
50EXCAVATION, TRANSPORTATION AND DISPOSAL OF DELINEATED SOIL31,268.00CY 6,668.00 0.006,668.00$21.00$140,028.00
71AC PAVEMENT (TEMPORARY ACCESS ROAD AND RAMP)1,500.00TON 1,312.00 1,277.0035.00$115.00$4,025.00
136OVERHEAD HEIGHT CLEARANCE SIGN2.00EA 2.00 0.002.00$1,400.00$2,800.00

DEDUCTION DETAIL

DescriptionUnitTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
LOCAL TARGATED WORKER HIRING PROGRAMSTIP 2,251.45 0.002,251.45$1.00 $2,251.45

FINANCIAL SUMMARY

  Total Previous Current
Earned $4,511,587.26 $206,465.02 $4,305,122.24
Retained $225,579.36 $10,323.25 $215,256.11
Deducted $2,251.45 $0.00 $2,251.45
Due $4,283,756.45 $196,141.77 $4,087,614.68