| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 3.00 | MTH |
3.00
| 2.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF BMPS | 1.00 | LS |
0.75
| 0.50 | 0.25 | $5,000.00 | $1,250.00 |
| 5 | OFFICE FACILITIES | 4.00 | MTH |
3.00
| 2.00 | 1.00 | $1,000.00 | $1,000.00 |
| 7 | TRAFFIC CONTROL | 1.00 | LS |
0.75
| 0.50 | 0.25 | $20,000.00 | $5,000.00 |
| 13 | STRUCTURE BACKFILL (RETAINING WALL) | 34.00 | CY |
34.00
| 20.00 | 14.00 | $300.00 | $4,200.00 |
| 17 | STRUCTURE CONCRETE (RETAINING WALL) | 53.00 | CY |
53.00
| 0.00 | 53.00 | $2,795.00 | $148,135.00 |
| 18 | BAR REINFORCING STEEL | 8,000.00 | LB |
8,000.00
| 6,000.00 | 2,000.00 | $5.00 | $10,000.00 |
| 19 | CABLE RAILING (CALTRANS STD PLAN B11-47) | 96.00 | LF |
96.00
| 0.00 | 96.00 | $75.00 | $7,200.00 |
| 28 | CONCRETE SURFACE TEXTURE | 865.00 | SF |
865.00
| 0.00 | 865.00 | $8.00 | $6,920.00 |