| Item No. | Description | Bid Qty | Units | Total Qty. | Previous Qty. | Current Qty. | Unit Price | Current Amount |
| 2 | CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH) | 34.00 | MTH |
2.00
| 1.00 | 1.00 | $500.00 | $500.00 |
| 4 | IMPLEMENTATION OF THE LTWHP | 1.00 | LS |
0.06
| 0.03 | 0.03 | $115,000.00 | $3,450.00 |
| 6 | IMPLEMENTATION OF THE SWPPP | 1.00 | LS |
0.06
| 0.03 | 0.03 | $300,000.00 | $9,000.00 |
| 9 | IMPLEMENTATION OF THE SITE-SPECIFIC LEAD COMPLIANCE PLAN | 1.00 | LS |
1.00
| 0.75 | 0.25 | $75,000.00 | $18,750.00 |
| 10 | DISPOSAL OF LEAD CONTAINING PAINT WASTE | 1.00 | LS |
1.00
| 0.00 | 1.00 | $5,000.00 | $5,000.00 |
| 12 | IMPLEMENTATION OF THE FUGITIVE DUST CONTROL PLAN | 34.00 | MTH |
2.00
| 1.00 | 1.00 | $8,000.00 | $8,000.00 |
| 15 | VEHICLES AND EQUIPMENT EMISSIONS REPORTING | 34.00 | MTH |
2.00
| 1.00 | 1.00 | $8,000.00 | $8,000.00 |
| 18 | NOISE MONITORING AND REPORTING | 34.00 | MTH |
2.00
| 1.00 | 1.00 | $6,000.00 | $6,000.00 |
| 20 | IMPLEMENTATION OF THE QUALITY CONTROL PROGRAM FOR MOISTURE CONTENT | 682.00 | DAY |
22.00
| 3.00 | 19.00 | $1,000.00 | $19,000.00 |
| 22 | OFFICE FACILITIES | 34.00 | MTH |
2.00
| 1.00 | 1.00 | $5,000.00 | $5,000.00 |
| 25 | MAINTENANCE OF TIRE WASHES | 90.00 | MTH |
2.00
| 1.00 | 1.00 | $3,500.00 | $3,500.00 |
| 26 | WATER TRUCKS | 682.00 | DAY |
39.00
| 20.00 | 19.00 | $1,500.00 | $28,500.00 |
| 27 | STREET SWEEPING | 682.00 | DAYS |
35.00
| 16.00 | 19.00 | $1,500.00 | $28,500.00 |
| 30 | MAINTENANCE OF TEMPORARY SOUND BARRIER | 5,800.00 | LF |
342.00
| 171.00 | 171.00 | $23.00 | $3,933.00 |
| 46 | AGENCY EXCLUDES 2013 MODEL YEAR ENGINE TRUCK | 2,115,914.00 | TON |
57,530.00
| 0.00 | 57,530.00 | $0.01 | $575.30 |
| 47 | AGENCY EXCLUDES 2014 MODEL YEAR ENGINE TRUCK | 2,115,914.00 | TON |
43,297.00
| 0.00 | 43,297.00 | $0.01 | $432.97 |
| 48 | AGENCY EXCLUDES 2015 MODEL YEAR ENGINE TRUCK | 2,115,914.00 | TON |
31,073.00
| 0.00 | 31,073.00 | $0.01 | $310.73 |
| 49 | EXCAVATION, TRANSPORTATION AND DISPOSAL OF EXCESS BASIN MATERIAL | 1,343,403.00 | CY |
44,048.00
| 7,903.00 | 36,145.00 | $15.00 | $542,175.00 |
| 72 | AC PAVEMENT (TEMPORARY ACCESS ROAD MAINTENANCE) | 1,500.00 | TON |
90.00
| 0.00 | 90.00 | $25.00 | $2,250.00 |
|