Los Angeles County Public Works
Project Management Division III
Progress Payment 8
Project Name: West Coast Basin Barrier Project Unit 13
Contractor: Environmental Construction, Inc.
21550 Oxnard Street, Suite 1060
Woodland Hills, CA 91367
Project ID: FCC0001322
Federal Number(s): None
Original Contract: $10,182,790.00
Awarded: 10/26/2020
Period Ending: 12/31/2021
Board Accepted: 2/13/2023
Item No.DescriptionBid QtyUnitsTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
2CONSTRUCTION SCHEDULE (UPDATE) (STIPULATED UNIT PRICE OF $500/MONTH)13.00MTH 8.00 7.001.00$500.00$500.00
4IMPLEMENTATION OF THE LTWHP1.00LS 0.64 0.560.08$2,000.00$160.00
5IMPLEMENTATION OF BMPS1.00LS 0.64 0.560.08$20,000.00$1,600.00
6RESTORATION OF EXISTING IMPROVEMENTS1.00LS 0.48 0.320.16$72,300.00$11,568.00
7SHORING OF OPEN EXCAVATIONS1.00LS 0.64 0.560.08$3,110.00$248.80
9IMPLEMENTATION OF THE SITE-SPECIFIC HEALTH AND SAFETY PLAN 1.00LS 0.64 0.560.08$5,000.00$400.00
11IMPLEMENTATION OF THE SITE-SPECIFIC ASBESTOS ABATEMENT PLAN1.00LS 1.00 0.500.50$23,500.00$11,750.00
12OFFICE FACILITIES13.00MTH 8.00 7.001.00$2,000.00$2,000.00
18CONCRETE REMOVAL (NON-REINFORCED)22.00CY 22.00 15.007.00$400.00$2,800.00
19UNCLASSIFIED EXCAVATION1,490.00CY 945.00 675.00270.00$45.00$12,150.00
32TRAFFIC CONTROL1.00LS 0.71 0.630.08$90,300.00$7,224.00
35LANDSCAPING1.00LS 0.40 0.300.10$81,355.00$8,135.50
3712" DIAM BLANK STAINLESS STEEL CASING1,469.00VF 1,014.00 896.00118.00$357.00$42,126.00
39GRAVEL PACK 24" DIAM HOLE1,595.00VF 1,094.00 951.00143.00$161.00$23,023.00
40GRAVEL PACK 30" DIAM HOLE11.00VF 2.00 0.002.00$576.00$1,152.00
41USE OF CONTRACTOR'S DRILL RIG190.00HR 20.00 19.001.00$170.00$170.00
424" DIAM PVC CONDUCTOR PIPE1,143.00VF 80.00 0.0080.00$17.00$1,360.00
47IMPLEMENTATION OF THE GROUNDWATER MANAGEMENT PLAN1.00LS 0.76 0.680.08$540,931.00$43,274.48
49NOISE CONTROL (ALLOWANCE OF 70,000)70,000.00AL 86,715.00 69,999.0016,716.00$1.00$16,716.00
50WELL DESTRUCTION OF EXISTING INJECTION WELLS9.00EA 9.00 6.003.00$22,600.00$67,800.00
52ABANDON VAULT3.00EA 0.00 3.00-3.00$1,500.00($4,500.00)
53DRILL PILOT HOLE3,502.00VF 2,836.00 2,561.00275.00$479.00$131,725.00
55DRILL 24" DIAMETER BOREHOLE1,805.00VF 1,167.00 1,017.00150.00$316.00$47,400.00
56DRILL 30" DIAMETER BOREHOLE1,029.00VF 646.00 573.0073.00$320.00$23,360.00
62GROUT 30" DIAMETER BOREHOLE1,006.00VF 982.00 821.00161.00$129.00$20,769.00
65SAND FILTER PACK FOR 30" DIAMETER BOREHOLE22.00VF 16.00 14.002.00$111.00$222.00
67PRECAST INJECTION WELL VAULT11.00EA 6.00 5.001.00$36,000.00$36,000.00
70WELL BOTTOM CAP (BULL NOSE)11.00EA 8.00 7.001.00$904.00$904.00
7112" DIAMETER STAINLESS STEEL SCREEN CASING1,495.00VF 945.00 820.00125.00$184.00$23,000.00
743" DIAMETER TREMIE PIPE SCHEDULE 80 PVC2,846.00VF 1,782.00 1,576.00206.00$9.00$1,854.00
78PRIMARY WELL DEVELOPMENT WITH SWABBING AND AIRLIFTING550.00HR 180.00 170.509.50$542.00$5,149.00
80ELECTRICAL WORK1.00LS 0.56 0.510.05$751,723.00$37,586.15
81FIELD INSTRUMENTS1.00LS 0.82 0.660.16$241,320.00$38,611.20
87PCC EDGING1,474.00LF 874.00 644.00230.00$54.00$12,420.00

DEDUCTION DETAIL

DescriptionUnitTotal Qty.Previous Qty.Current Qty.Unit PriceCurrent Amount
OVERTIME INSPECTIONHOUR 92.50 97.50-5.00$100.00 ($500.00)

FINANCIAL SUMMARY

  Total Previous Current
Earned $7,019,281.44 $6,390,623.31 $628,658.13
Retained* $350,964.07 $319,531.17 $31,432.90
Deducted $9,250.00 $9,750.00 ($500.00)
Due $6,659,067.37 $6,061,342.14 $597,725.23



*This project has an escrow account.

Contact Office Engineer