Los Angeles County Public Works
Project Management Division III
Progress Payment 16
Project Name: Sierra Madre Dam Slope Protection And Basin Access Road Improvement Project
Contractor: GMZ Engineering, Inc.
5655 Lindero Canyon Road #430
Westlake Village, CA 91362
Project ID: FCC0001291
Federal Number(s): None
Original Contract: $4,071,119.00
Awarded: 6/18/2020
Period Ending: 12/27/2022
There is NO item progress this period

DEDUCTION DETAIL

There are NO deductions this period

FINANCIAL SUMMARY

  Total Previous Current
Earned $4,107,139.14 $4,107,139.14 $0.00
Retained $102,678.52 $205,356.98 ($102,678.46)
Deducted $0.00 $0.00 $0.00
Due $4,004,460.62 $3,901,782.16 $102,678.46



Contact Office Engineer
Mercedes Passanisi (626) 458-3142
Contractor Copy  